Filter by category
Filter by Date
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 10/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1830 hrs 10/12/2024 to 1900 hrs 10/12/2024.
The forecast capacity reserve requirement is 1385 MW.
The minimum capacity reserve available is 1336 MW.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 17/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
1. From 1700 hrs to 1830 hrs 17/12/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1310 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
1. From 1500 hrs 16/12/2024 to 1630 hrs 16/12/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 700 MW.
2. From 1930 hrs to 2030 hrs 16/12/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 962 MW.
AEMO Operations
[EventId:202412091800_review] Prices for interval 09-Dec-2024 18:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1755 hrs on 9 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 09-Dec-2024 18:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412091755_review] Prices for interval 09-Dec-2024 17:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1750 hrs on 9 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 09-Dec-2024 17:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412091750_review] Prices for interval 09-Dec-2024 17:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1745 hrs on 9 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 09-Dec-2024 17:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412091745_review] Prices for interval 09-Dec-2024 17:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1740 hrs on 9 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 09-Dec-2024 17:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412091740_review] Prices for interval 09-Dec-2024 17:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1735 hrs on 9 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 09-Dec-2024 17:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412091735_review] Prices for interval 09-Dec-2024 17:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 9 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 09-Dec-2024 17:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.