121286INTER-REGIONAL TRANSFER30/11/2024 11:36:18 AM

Inter-regional transfer limit variation - Red Cliffs - Wemen 220 kV line - VIC region - 30/11/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Red Cliffs - Wemen 220 kV line - VIC region - 30/11/2024

A planned outage of Red Cliffs - Wemen 220 kV line in the VIC region was scheduled from 0400 hrs 30/11/2024 to 1430 hrs 30/11/2024.

The outage has been completed and Red Cliffs - Wemen 220 kV line returned to service at 1120 hrs 30/11/2024

Constraint set(s) revoked: V-KG_WE_RC

Manager NEM Real Time Operations
     
121147INTER-REGIONAL TRANSFER28/11/2024 12:32:16 PM

Cancellation - Inter-regional transfer limit variation - to manage Power System Security in NSW region - 28/11/2024

AEMO ELECTRICITY MARKET NOTICE

Refer AEMO Electricity Market Notice 121142

Constraint set I-QN_1000 was invoked from 0955 hrs until 1230 hrs 28/11/2024.

This constraint set contains equations with the following interconnector on the LHS;

NSW1-QLD1

Manager NEM Real Time Operations
     
121142INTER-REGIONAL TRANSFER28/11/2024 10:02:47 AM

Inter-regional transfer limit variation - to manage Power System Security in NSW region - 28/11/2024

AEMO ELECTRICITY MARKET NOTICE

In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked the following constraint set I-QN_1000 from 0955 hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;

NSW1-QLD1

Manager NEM Real Time Operations
     
121138GENERAL NOTICE28/11/2024 09:37:07 AM

Planned outage of the Red Cliffs - Wemen - Kerang 220kV line in the VIC region on 30/11/2024.

AEMO ELECTRICITY MARKET NOTICE

The Red Cliffs - Wemen - Kerang 220kV line in the Victorian (VIC) region is planned to be out of service from 0400 hrs to 1430 hrs on 30/11/2024.

A credible contingency event during this planned outage may require:
- Load shedding in the Victorian outer grid; and/ or
- Market intervention, such as the issuing of directions.

Refer AEMO Network Outage Schedule (NOS) for further details.

AEMO Operations
     
121105RESERVE NOTICE27/11/2024 04:45:09 PM

Cancellation of Actual (LOR2) condition in the NSW region - 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR2) condition in the NSW region - 27/11/2024

The Actual LOR2 Condition in the NSW Region advised in AEMO Electricity Market Notice No.121101 is cancelled at 1645 hrs 27/11/2024.

Manager NEM Real Time Operations
     
121101RESERVE NOTICE27/11/2024 03:48:50 PM

Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 27/11/2024

An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1530 hrs.

The Actual LOR2 condition is forecast to exist until 1700 hrs.
The capacity reserve required is 685 MW
The minimum reserve available is 412 MW

AEMO is seeking an immediate market response.

Manager NEM Real Time Operations
     
121056RESERVE NOTICE27/11/2024 11:31:02 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 121040 is cancelled at 1130 hrs 27/11/2024

Manager NEM Real Time Operations
     
121040RESERVE NOTICE27/11/2024 10:19:18 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 121021 has been updated at 1000 hrs to the following:

[1.] From 1530 hrs 27/11/2024 to 1700 hrs 27/11/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 87 MW at 1530 hrs.

AEMO is seeking a market response.

AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 1330 hrs.

Manager NEM Real Time Operations
     
121021RESERVE NOTICE27/11/2024 07:27:45 AM

PDPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1530 hrs 27/11/2024 to 1700 hrs 27/11/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 84 MW at approximately 1530 hrs.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.