Market Notices

121228PRICES UNCHANGED29/11/2024 07:12:48 AM

[EventId:202411290700_confirmed] Prices for interval 29-Nov-2024 07:00 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0710 hrs on 29 November 2024

PRICES ARE NOW CONFIRMED for trading interval 29-Nov-2024 07:00.

In accordance with Market Notice 121222 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
121227PRICES UNCHANGED29/11/2024 07:11:45 AM

[EventId:202411290655_confirmed] Prices for interval 29-Nov-2024 06:55 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0710 hrs on 29 November 2024

PRICES ARE NOW CONFIRMED for trading interval 29-Nov-2024 06:55.

In accordance with Market Notice 121221 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
121226PRICES UNCHANGED29/11/2024 07:10:23 AM

[EventId:202411290645_confirmed] Prices for interval 29-Nov-2024 06:45 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0710 hrs on 29 November 2024

PRICES ARE NOW CONFIRMED for trading interval 29-Nov-2024 06:45.

In accordance with Market Notice 121219 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
121218RESERVE NOTICE29/11/2024 05:26:03 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region [beginning] on 29/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121217 is cancelled at 0525 hrs 29/11/2024.

Manager NEM Real Time Operations
     
121217RESERVE NOTICE29/11/2024 05:00:17 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 29/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121216 has been updated at 0500 hrs to the following:

[1.] From 1430 hrs 29/11/2024 to 1500 hrs 29/11/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1428 MW.

Manager NEM Real Time Operations
     
121216RESERVE NOTICE28/11/2024 11:37:33 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 29/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121215 has been updated at 2330 hrs to the following:

[1.] From 0800 hrs 29/11/2024 to 0930 hrs 29/11/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1387 MW.

[2.] From 1430 hrs 29/11/2024 to 1700 hrs 29/11/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1286 MW.

Manager NEM Real Time Operations
     
121215RESERVE NOTICE28/11/2024 10:02:05 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 29/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121173 has been updated at 2200 hrs to the following:

[1.] From 1430 hrs 29/11/2024 to 1530 hrs 29/11/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1409 MW.

Manager NEM Real Time Operations
     
121214RECLASSIFY CONTINGENCY28/11/2024 07:44:16 PM

Cancellation of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV

Cancellation time: 28/11/2024 19:44

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 121145

Auto-generated on behalf of Manager NEM Real Time Operations
     
121213PRICES UNCHANGED28/11/2024 07:47:27 PM

[EventId:202411281920_confirmed] Prices for interval 28-Nov-2024 19:20 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1940 hrs on 28 November 2024

PRICES ARE NOW CONFIRMED for trading interval 28-Nov-2024 19:20.

In accordance with Market Notice 121201 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm