118243RECLASSIFY CONTINGENCY11/09/2024 05:28:40 PM

Reclassification of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV

Duration: 11/09/2024 17:28 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
118233PRICES SUBJECT TO REVIEW11/09/2024 01:20:20 PM

[EventId:202409111325_review] Prices for interval 11-Sep-2024 13:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1320 hrs on 11 September 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 11-Sep-2024 13:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118232PRICES SUBJECT TO REVIEW11/09/2024 01:15:47 PM

[EventId:202409111320_review] Prices for interval 11-Sep-2024 13:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1315 hrs on 11 September 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 11-Sep-2024 13:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118230PRICES SUBJECT TO REVIEW11/09/2024 01:10:30 PM

[EventId:202409111315_review] Prices for interval 11-Sep-2024 13:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1310 hrs on 11 September 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 11-Sep-2024 13:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118229PRICES SUBJECT TO REVIEW11/09/2024 01:05:27 PM

[EventId:202409111310_review] Prices for interval 11-Sep-2024 13:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1305 hrs on 11 September 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 11-Sep-2024 13:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118228PRICES SUBJECT TO REVIEW11/09/2024 01:00:17 PM

[EventId:202409111305_review] Prices for interval 11-Sep-2024 13:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1300 hrs on 11 September 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 11-Sep-2024 13:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118227PRICES SUBJECT TO REVIEW11/09/2024 12:55:24 PM

[EventId:202409111300_review] Prices for interval 11-Sep-2024 13:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1255 hrs on 11 September 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 11-Sep-2024 13:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118226GENERAL NOTICE10/09/2024 05:55:51 PM

Network Augmentation Commissioned - NSW Region - 10/09/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - NSW Region - 10/09/2024

At 1750 hrs, the following equipment at Buronga 330 kV substation has been commissioned:

1) Buronga 330 kV A bus.
2) Buronga 330 kV B bus.
3) Buronga No 1 330 kV capacitor.
4) Buronga No 2 330 kV capacitor.
5) Buronga No 7 330/220 kV transformer.

Manager NEM Real Time Operations
     
118214NON-CONFORMANCE10/09/2024 04:10:15 AM

NON-CONFORMANCE Region QLD1 Tuesday, 10 September 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Tuesday, 10 September 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 10/09/2024 03:50 to 10/09/2024 04:10
Amount: 39 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     