Market Notices

121987RECLASSIFY CONTINGENCY15/12/2024 06:19:25 PM

Cancellation of a Non-Credible Contingency Event: Tumoulin - Woree No.877 275 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Tumoulin - Woree No.877 275 kV and Chalumbin - Turkinje No.7166 132 kV

Cancellation time: 15/12/2024 18:19

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 121970

Auto-generated on behalf of Manager NEM Real Time Operations
     
121986RECLASSIFY CONTINGENCY15/12/2024 06:19:20 PM

Cancellation of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV

Cancellation time: 15/12/2024 18:19

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 121969

Auto-generated on behalf of Manager NEM Real Time Operations
     
121985RECLASSIFY CONTINGENCY15/12/2024 05:19:23 PM

Cancellation of a Non-Credible Contingency Event: Collinsville - Stoney Creek 7306 132KV LINE line and Collinsville - Newlands 7121 132KV LINE line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Collinsville - Stoney Creek 7306 132KV LINE and Collinsville - Newlands 7121 132KV LINE

Cancellation time: 15/12/2024 17:19

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 121971

Auto-generated on behalf of Manager NEM Real Time Operations
     
121984SETTLEMENTS RESIDUE15/12/2024 05:13:07 PM

[EventId:202412151705_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 15 December 2024 17:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1705 hrs on 15 December 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 December 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1705 hrs on 15 December 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
121983PRICES UNCHANGED15/12/2024 05:10:24 PM

[EventId:202412151645_confirmed] Prices for interval 15-Dec-2024 16:45 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1705 hrs on 15 December 2024

PRICES ARE NOW CONFIRMED for trading interval 15-Dec-2024 16:45.

In accordance with Market Notice 121973 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
121982PRICES UNCHANGED15/12/2024 05:09:13 PM

[EventId:202412151705_confirmed] Prices for interval 15-Dec-2024 17:05 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1705 hrs on 15 December 2024

PRICES ARE NOW CONFIRMED for trading interval 15-Dec-2024 17:05.

In accordance with Market Notice 121977 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
121981PRICES UNCHANGED15/12/2024 05:08:12 PM

[EventId:202412151700_confirmed] Prices for interval 15-Dec-2024 17:00 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1705 hrs on 15 December 2024

PRICES ARE NOW CONFIRMED for trading interval 15-Dec-2024 17:00.

In accordance with Market Notice 121976 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
121980PRICES UNCHANGED15/12/2024 05:07:03 PM

[EventId:202412151655_confirmed] Prices for interval 15-Dec-2024 16:55 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1705 hrs on 15 December 2024

PRICES ARE NOW CONFIRMED for trading interval 15-Dec-2024 16:55.

In accordance with Market Notice 121975 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
121979PRICES UNCHANGED15/12/2024 05:11:51 PM

[EventId:202412151650_confirmed] Prices for interval 15-Dec-2024 16:50 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1705 hrs on 15 December 2024

PRICES ARE NOW CONFIRMED for trading interval 15-Dec-2024 16:50.

In accordance with Market Notice 121974 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm