NON-CONFORMANCE Region NSW1 Friday, 6 December 2024
NON-CONFORMANCE NSW1 Region Friday, 6 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP5
Duration: 06/12/2024 09:10 to 06/12/2024 09:35
Amount: -45 MW
Constraint: NC-N_VP5
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202412051330_review] Prices for interval 05-Dec-2024 13:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1325 hrs on 5 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 05-Dec-2024 13:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412051325_review] Prices for interval 05-Dec-2024 13:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1320 hrs on 5 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 05-Dec-2024 13:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412051320_review] Prices for interval 05-Dec-2024 13:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1315 hrs on 5 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 05-Dec-2024 13:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412051315_review] Prices for interval 05-Dec-2024 13:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1310 hrs on 5 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 05-Dec-2024 13:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412051310_review] Prices for interval 05-Dec-2024 13:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1305 hrs on 5 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 05-Dec-2024 13:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412051300_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 05 December 2024 13:00
Issued by Australian Energy Market Operator Ltd at 1300 hrs on 5 December 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 5 December 2024.
Refer to market notice: 121473
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.
The negative residue constraint NRM_QLD1_NSW1 ceased operating at 1300 hrs on 5 December 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202412051305_review] Prices for interval 05-Dec-2024 13:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1300 hrs on 5 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 05-Dec-2024 13:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412051200_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 05 December 2024 12:00
Issued by Australian Energy Market Operator Ltd at 1200 hrs on 5 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 5 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.
The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1200 hrs on 5 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1
The RHS of the constraint equation may be adjusted to manage residues.