Market Notices

121500NON-CONFORMANCE06/12/2024 09:35:21 AM

NON-CONFORMANCE Region NSW1 Friday, 6 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Friday, 6 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP5
Duration: 06/12/2024 09:10 to 06/12/2024 09:35
Amount: -45 MW
Constraint: NC-N_VP5

Auto-generated on behalf of Manager NEM Real Time Operations
     
121466NON-CONFORMANCE04/12/2024 09:05:45 PM

NON-CONFORMANCE Region VIC1 Wednesday, 4 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Wednesday, 4 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: GANNB1
Duration: 04/12/2024 20:55 to 04/12/2024 21:05
Amount: -24 MW
Constraint: NC-V_GANNB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
121444NON-CONFORMANCE04/12/2024 06:40:18 AM

NON-CONFORMANCE Region NSW1 Wednesday, 4 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Wednesday, 4 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP6
Duration: 04/12/2024 06:25 to 04/12/2024 06:40
Amount: -16 MW
Constraint: NC-N_VP6

Auto-generated on behalf of Manager NEM Real Time Operations
     
121413NON-CONFORMANCE03/12/2024 11:15:53 AM

NON-CONFORMANCE Region NSW1 Tuesday, 3 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Tuesday, 3 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP6
Duration: 03/12/2024 11:05 to 03/12/2024 11:15
Amount: -58 MW
Constraint: NC-N_VP6

Auto-generated on behalf of Manager NEM Real Time Operations
     
121387RESERVE NOTICE02/12/2024 07:22:04 PM

Cancellation of Actual (LOR1) condition in the NSW region - 02/12/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 02/12/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.121384 is cancelled at 1920 hrs 02/12/2024.

Manager NEM Real Time Operations
     
121384RESERVE NOTICE02/12/2024 05:16:49 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 02/12/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 02/12/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs

The capacity reserve requirement is 1370 MW
The minimum capacity reserve available is 1066 MW

Manager NEM Real Time Operations
     
121312NON-CONFORMANCE01/12/2024 12:20:24 PM

NON-CONFORMANCE Region NSW1 Sunday, 1 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Sunday, 1 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: GOONSF1
Duration: 01/12/2024 11:50 to 01/12/2024 12:20
Amount: 54 MW
Constraint: NC-N_GOONSF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
121310NON-CONFORMANCE01/12/2024 11:20:24 AM

NON-CONFORMANCE Region NSW1 Sunday, 1 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Sunday, 1 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: GOONSF1
Duration: 01/12/2024 09:55 to 01/12/2024 11:20
Amount: 35 MW
Constraint: NC-N_GOONSF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
121295RESERVE NOTICE30/11/2024 04:40:16 PM

STPASA - Update of the suspect Lack Of Reserve Level 3 (LOR3) condition in the NSW Region on 06/12/2024

AEMO ELECTRICITY MARKET NOTICE

The suspect LOR3 condition advised in AEMO Electricity Market Notice No. 121292 has been reviewed.

AEMO considers this forecast LOR3 condition invalid. Subsequent STPASA runs are producing valid solutions.


AEMO Operations
     