121648RESERVE NOTICE08/12/2024 11:33:43 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 121647 is cancelled at 2330 hrs 08/12/2024.

AEMO Operations
     
121647RESERVE NOTICE08/12/2024 09:42:45 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

[1.] From 1430 hrs 10/12/2024 to 1500 hrs 10/12/2024.
The forecast capacity reserve requirement is 819 MW.
The minimum capacity reserve available is 802 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
121627INTER-REGIONAL TRANSFER08/12/2024 04:05:37 PM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 08/12/2024

AEMO ELECTRICITY MARKET NOTICE

In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked automated constraint set CA_BRIS_5667C22F from 1600 hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;

N-Q-MNSP1

Refer to AEMO Network Outage Scheduler (NOS) for further information.

Manager NEM Real Time Operations
     
121614INTER-REGIONAL TRANSFER08/12/2024 04:00:08 AM

Inter-regional transfer limit variation - Glenn Innes to Tenterfield 96R 132kV line- NSW region - 08/12/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation -Glenn Innes to Tenterfield 96R 132kV line - NSW region - 08/12/2024

At 0333 hrs 08/12/2024 there was an unplanned outage of Glenn Innes to Tenterfield 96R 132kV line.

The following constraint set(s) invoked at 0345 hrs 08/12/2024
N-96L_96R_CB4102

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
121606NON-CONFORMANCE07/12/2024 06:50:23 PM

NON-CONFORMANCE Region QLD1 Saturday, 7 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Saturday, 7 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 07/12/2024 18:45 to 07/12/2024 18:50
Amount: -12 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
121557NON-CONFORMANCE07/12/2024 03:40:14 AM

NON-CONFORMANCE Region NSW1 Saturday, 7 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Saturday, 7 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 07/12/2024 03:30 to 07/12/2024 03:40
Amount: -6 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
121500NON-CONFORMANCE06/12/2024 09:35:21 AM

NON-CONFORMANCE Region NSW1 Friday, 6 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Friday, 6 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP5
Duration: 06/12/2024 09:10 to 06/12/2024 09:35
Amount: -45 MW
Constraint: NC-N_VP5

Auto-generated on behalf of Manager NEM Real Time Operations
     
121466NON-CONFORMANCE04/12/2024 09:05:45 PM

NON-CONFORMANCE Region VIC1 Wednesday, 4 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Wednesday, 4 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: GANNB1
Duration: 04/12/2024 20:55 to 04/12/2024 21:05
Amount: -24 MW
Constraint: NC-V_GANNB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
121444NON-CONFORMANCE04/12/2024 06:40:18 AM

NON-CONFORMANCE Region NSW1 Wednesday, 4 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Wednesday, 4 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP6
Duration: 04/12/2024 06:25 to 04/12/2024 06:40
Amount: -16 MW
Constraint: NC-N_VP6

Auto-generated on behalf of Manager NEM Real Time Operations
     