Market Notices

118359RESERVE NOTICE21/09/2024 03:02:14 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 22/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 118358 is cancelled at 1500 hrs 21/09/2024.

Manager NEM Real Time Operations
     
118358RESERVE NOTICE21/09/2024 12:56:24 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 22/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:

[1.] From 1930 hrs 22/09/2024 to 2030 hrs 22/09/2024.
The forecast capacity reserve requirement is 600 MW.
The minimum capacity reserve available is 545 MW.

Manager NEM Real Time Operations
     
118357MARKET INTERVENTION21/09/2024 03:03:21 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 118339

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 1600 hrs 22/09/2024.

The direction update is issued at 1500 hrs 21/09/2024.

Manager NEM Real Time Operations
     
118356MARKET INTERVENTION21/09/2024 03:00:51 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 118340

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1600 hrs 22/09/2024.

The direction update is issued at 1500 hrs 21/09/2024.

Manager NEM Real Time Operations
     
118348MARKET INTERVENTION20/09/2024 11:34:36 PM

Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS

Refer to Market Notice 118337

Direction is cancelled from: 2330 hrs 20/09/2024

Manager NEM Real Time Operations
     
118341MARKET INTERVENTION20/09/2024 04:30:22 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - BARKER INLET PS

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - BARKER INLET PS

Refer to Market Notice 118336

Direction is cancelled from: 1630 hrs 20/09/2024

Manager NEM Real Time Operations
     
118340MARKET INTERVENTION20/09/2024 04:03:19 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer AEMO Electricity Market Notice 118330

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 22/09/2024.

The direction update is issued at 1600 hrs 20/09/2024.

Manager NEM Real Time Operations
     
118339MARKET INTERVENTION20/09/2024 04:01:47 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Market Notice 118334

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 1730 hrs 21/09/2024.

The direction update is issued at 1600 hrs 20/09/2024.

Manager NEM Real Time Operations
     
118338MARKET INTERVENTION20/09/2024 04:00:11 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer to Market Notice 118332

Direction is cancelled from: 1100 hrs 20/09/2024

Manager NEM Real Time Operations
     