Filter by category
Filter by Date
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/12/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
[1.] From 1430 hrs 10/12/2024 to 1500 hrs 10/12/2024.
The forecast capacity reserve requirement is 819 MW.
The minimum capacity reserve available is 802 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
[EventId:202412081835_review] Prices for interval 08-Dec-2024 18:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1830 hrs on 8 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Dec-2024 18:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412081830_review] Prices for interval 08-Dec-2024 18:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1825 hrs on 8 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Dec-2024 18:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412081825_review] Prices for interval 08-Dec-2024 18:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1820 hrs on 8 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Dec-2024 18:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412081820_review] Prices for interval 08-Dec-2024 18:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1815 hrs on 8 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Dec-2024 18:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412081815_review] Prices for interval 08-Dec-2024 18:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1810 hrs on 8 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Dec-2024 18:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412081810_review] Prices for interval 08-Dec-2024 18:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1805 hrs on 8 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Dec-2024 18:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412081805_review] Prices for interval 08-Dec-2024 18:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 8 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Dec-2024 18:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region QLD1 Saturday, 7 December 2024
NON-CONFORMANCE QLD1 Region Saturday, 7 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 07/12/2024 18:45 to 07/12/2024 18:50
Amount: -12 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations