121129RECLASSIFY CONTINGENCY27/11/2024 09:14:22 PM

Cancellation of a Non-Credible Contingency Event: Yallourn - Rowville 7 220 kV line and Yallourn - Rowville 8 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: VIC1

Lines: Yallourn - Rowville 7 220 kV and Yallourn - Rowville 8 220 kV

Cancellation time: 27/11/2024 21:14

Constraint set(s) revoked:
V-ROYP78_R_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Refer AEMO Electricity Market Notice 121073

Auto-generated on behalf of Manager NEM Real Time Operations
     
121126PRICES UNCHANGED27/11/2024 06:34:52 PM

[EventId:202411271805_confirmed] Prices for interval 27-Nov-2024 18:05 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1830 hrs on 27 November 2024

PRICES ARE NOW CONFIRMED for trading interval 27-Nov-2024 18:05.

In accordance with Market Notice 121115 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
121125PRICES UNCHANGED27/11/2024 06:36:24 PM

[EventId:202411271830_confirmed] Prices for interval 27-Nov-2024 18:30 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1830 hrs on 27 November 2024

PRICES ARE NOW CONFIRMED for trading interval 27-Nov-2024 18:30.

In accordance with Market Notice 121120 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
121124PRICES UNCHANGED27/11/2024 06:33:43 PM

[EventId:202411271825_confirmed] Prices for interval 27-Nov-2024 18:25 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1830 hrs on 27 November 2024

PRICES ARE NOW CONFIRMED for trading interval 27-Nov-2024 18:25.

In accordance with Market Notice 121119 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
121123PRICES UNCHANGED27/11/2024 06:32:48 PM

[EventId:202411271820_confirmed] Prices for interval 27-Nov-2024 18:20 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1830 hrs on 27 November 2024

PRICES ARE NOW CONFIRMED for trading interval 27-Nov-2024 18:20.

In accordance with Market Notice 121118 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
121122PRICES UNCHANGED27/11/2024 06:31:49 PM

[EventId:202411271815_confirmed] Prices for interval 27-Nov-2024 18:15 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1830 hrs on 27 November 2024

PRICES ARE NOW CONFIRMED for trading interval 27-Nov-2024 18:15.

In accordance with Market Notice 121117 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
121121PRICES UNCHANGED27/11/2024 06:30:21 PM

[EventId:202411271810_confirmed] Prices for interval 27-Nov-2024 18:10 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1830 hrs on 27 November 2024

PRICES ARE NOW CONFIRMED for trading interval 27-Nov-2024 18:10.

In accordance with Market Notice 121116 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
121105RESERVE NOTICE27/11/2024 04:45:09 PM

Cancellation of Actual (LOR2) condition in the NSW region - 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR2) condition in the NSW region - 27/11/2024

The Actual LOR2 Condition in the NSW Region advised in AEMO Electricity Market Notice No.121101 is cancelled at 1645 hrs 27/11/2024.

Manager NEM Real Time Operations
     
121101RESERVE NOTICE27/11/2024 03:48:50 PM

Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 27/11/2024

An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1530 hrs.

The Actual LOR2 condition is forecast to exist until 1700 hrs.
The capacity reserve required is 685 MW
The minimum reserve available is 412 MW

AEMO is seeking an immediate market response.

Manager NEM Real Time Operations
     