Market Notices

120836INTER-REGIONAL TRANSFER22/11/2024 07:32:00 PM

Inter-regional transfer limit variation - Directlink - NSW region - 22/11/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Directlink - NSW region - 22/11/2024

At 1911 hrs 22/11/2024 there was an unplanned outage of the No.2 leg of Directlink.

The following constraint set(s) invoked at 1920 hrs 22/11/2024
N-X_MBTE_2

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
120831INTER-REGIONAL TRANSFER22/11/2024 05:29:01 PM

Inter-Regional Transfer limit variation - Directlink - NSW Region

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink - NSW Region

There has been an unplanned outage of the No 2 Leg of Directlink .

The following constraint set was invoked at 1720 hrs 22/11/2024

N-X_MBTE_2

The constraint set contains the following interconnector on the left hand side.

N-Q-MNSP1

Refer AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
     
120701RECALL GEN CAPACITY20/11/2024 08:08:03 AM

Request for Generator Recall Information for the period from 25/11/2024 to 26/11/2024 for NSW Region

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice no. 120700, 120699 and 120698.

Please provide Generator Recall Information for the period from 25/11/2024 to 26/11/2024, by 1200 hrs on 21/11/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf

AEMO Operations
     
120682INTER-REGIONAL TRANSFER19/11/2024 04:44:40 PM

Inter-regional transfer limit variation - Moorabool - Sydenham No. 2 500 kV Line - VIC region - 19/11/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Moorabool - Sydenham No. 2 500 kV Line - VIC region - 19/11/2024

A planned outage of Moorabool - Sydenham No. 2 500 kV Line in the VIC region was scheduled from 1130 hrs 13/11/2024 to 1900 hrs 20/11/2024.

The outage has been completed and Moorabool - Sydenham No. 2 500 kV Line returned to service at 1640 hrs 19/11/2024

Constraint set(s) revoked: V-MLSY_NOEMTT_R

Manager NEM Real Time Operations
     
120616INTER-REGIONAL TRANSFER18/11/2024 04:02:01 PM

Inter-regional transfer limit variation - Southpine - Rocklea 809 275 kV Line - QLD region - 18/11/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Southpine - Rocklea 809 275 kV Line - QLD region - 18/11/2024

At 1545 hrs 18/11/2024 there was an unplanned outage of Southpine - Rocklea 809 275 kV Line.

The following constraint set(s) invoked at 1545 hrs 18/11/2024
Q-RLSP_809

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
120550INTER-REGIONAL TRANSFER17/11/2024 01:33:17 PM

Inter-regional transfer limit variation - Armidale to Dumaresq (8C) 330 kV line - NSW region - 17/11/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Armidale to Dumaresq (8C) 330 kV line - NSW region - 17/11/2024

A planned outage of Armidale to Dumaresq (8C) 330 kV line in the NSW region was scheduled from 0500 hrs 17/11/2024 to 1700 hrs 17/11/2024.

The outage has been completed returned to service at 1330 hrs 17/11/2024

Constraint set(s) revoked:
N-ARDM_8C
N-DM_SVC
N-TW_SVC
N-X_8C+DM+TW_SVC

Manager NEM Real Time Operations
     
120253INTER-REGIONAL TRANSFER11/11/2024 01:31:43 PM

Inter-regional transfer limit variation - Bungama - Davenport 275 kV line - SA region - 11/11/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Bungama - Davenport 275 kV line - SA region - 11/11/2024

At 1307 hrs 11/11/2024 there was an unplanned outage of the Bungama - Davenport 275 kV line.

The following constraint set invoked at 1315 hrs 11/11/2024
S-BGDV

This constraint sets contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
119893INTER-REGIONAL TRANSFER05/11/2024 08:48:29 AM

Inter-regional transfer limit variation - Tamworth No 3 330 kV bus and Tamworth - Uralla No. 85 330 kV Line - NSW region - 05/11/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Tamworth No 3 330 kV bus and Tamworth - Uralla No. 85 330 kV Line - NSW region - 05/11/2024

A planned outage of Tamworth No 3 330 kV bus and Tamworth - Uralla No. 85 330 kV Line in the NSW region was scheduled to be completed at 1700 hrs 05/11/2024

The outage has been completed by 0840 hrs 05/11/2024.

Constraint set(s) invoked:
N-MUTW_88
N-TWUL_85
N-TW_SVC
N-DM_SVC
N-X_TW_330_BUS3-5

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW1-QLD1
T-V-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
119826INTER-REGIONAL TRANSFER03/11/2024 01:10:08 PM

Inter-regional transfer limit variation - three poles of Directlink - NSW region - 03/11/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - three poles of Directlink - NSW region - 03/11/2024

At 1330 hrs 03/11/2024 there will be a short notice outage of all three poles of Directlink.

The following constraint set(s) to be invoked at 1330 hrs 03/11/2024
N-X_MBTE_3

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm