Foreseeable AEMO intervention in SA region
Foreseeable AEMO intervention in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0700 hrs 07/12/2024.
The foreseeable circumstance requiring the need for intervention is Voltage.
AEMO estimates that, in the absence of sufficient market response by 1615 hrs 06/12/2024, AEMO may need to intervene by issuing a direction.
Manager NEM Real Time Operations
Forecast Minimum System Load (MSL1) condition in the VIC region on 08/12/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 08/12/2024.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 1590 MW
o MSL2 - 1090 MW
o MSL3 - 590 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
1. From 1200 hrs 08/12/2024 to 1330 hrs 08/12/2024. Minimum regional demand is forecast to be 1496 MW at 1300 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
AEMO Operations
Cancellation - Foreseeable intervention to manage power system security in SA region 30/11/2024
Cancellation - Foreseeable intervention to manage power system security in SA region 30/11/2024
Refer Market Notice 121281
AEMO no longer foresees a possible requirement for intervention to manage power system security in SA region. The advice of possible intervention is cancelled from 0915 hrs 30/11/2024.
Manager NEM Real Time Operations
Update - Foreseeable AEMO intervention in SA region
Update - Foreseeable AEMO intervention in SA region
Refer AEMO Electricity Market Notice 121280
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 1100 hrs 30/11/2024.
The foreseeable circumstance requiring the need for intervention is Voltage.
AEMO estimates that, in the absence of sufficient market response by 0900 hrs 30/11/2024, AEMO may need to intervene by issuing a direction.
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 1100 hrs 30/11/2024.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 27/11/2024
Cancellation - AEMO Intervention Event - SA region 27/11/2024
Refer to Market Notice 121094
The AEMO Intervention Event and all associated directions are cancelled from 1500 hrs on 28/11/2024.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 121091
Direction is cancelled from: 1500 hrs 28/11/2024
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 121090
Direction is cancelled from: 1430 hrs 28/11/2024
Manager NEM Real Time Operations
End of RERT Dispatch - 27/11/2024 and End of intervention event
End of Reliability and Emergency Reserve Trader (RERT) dispatch for - NSW1 Region - 27/11/2024 and end of AEMO Intervention Event.
Refer AEMO Electricity Market Notices 121102
Activation of reserve contract(s) has ended.
The reserve contract(s) were activated from 15:45 hrs 27/11/2024 to 16:45 hrs 27/11/2024
The AEMO Intervention Event ended from 16:45 hrs 27/11/2024
Manager NEM Real Time Operations