Market Notices

121963MARKET INTERVENTION15/12/2024 02:41:24 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0130 hrs 17/12/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
121874RESERVE NOTICE13/12/2024 07:20:19 PM

Cancellation of Actual (LOR1) condition in the NSW region - 13/12/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 13/12/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.121872 is cancelled at 1915 hrs 13/12/2024.

Manager NEM Real Time Operations
     
121872RESERVE NOTICE13/12/2024 06:21:43 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/12/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/12/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs

The capacity reserve requirement is 1370 MW
The minimum capacity reserve available is 1359 MW

Manager NEM Real Time Operations
     
121806POWER SYSTEM EVENTS12/12/2024 08:52:19 PM

Non-credible contingency event - QLD region - 12/12/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 12/12/2024

At 2026 hrs the Kamerunga to Barron George 132 kV Line 7184 and the Kamerunga to Barron George 132 kV Line 7141 tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
     
121804RESERVE NOTICE12/12/2024 07:52:07 PM

Cancellation of Actual (LOR1) condition in the NSW region - 12/12/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 12/12/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.121803 is cancelled at 1945 hrs 12/12/2024.

Manager NEM Real Time Operations
     
121803RESERVE NOTICE12/12/2024 07:17:45 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW Region on 12/12/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 12/12/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1830 hrs.

The Actual LOR1 condition is forecast to exist until 1930 hrs.

The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1338 MW.


Manager NEM Real Time Operations
     
121766MARKET INTERVENTION12/12/2024 09:31:31 AM

Cancellation - AEMO Intervention Event - SA region 11/12/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 06/12/2024

Refer to Market Notice 121721

The AEMO Intervention Event and all associated directions are cancelled from 0930 hrs on 12/12/2024.


Manager NEM Real Time Operations
     
121763MARKET INTERVENTION12/12/2024 09:30:08 AM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer to Market Notice 121722

Direction is cancelled from: 0930 hrs 12/12/2024

Manager NEM Real Time Operations
     
121759RECALL GEN CAPACITY12/12/2024 09:09:42 AM

Request for Generator Recall Information for the period 16/12/2024 and 17/12/2024 for Region NSW

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice no. 121760, 121762, and 121765.

Please provide Generator Recall Information for the period from 16/12/2024 to 17/12/2024, by 1200 hrs on 13/12/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf


AEMO Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm