Inter-Regional Transfer limit variation - Murraylink
Inter-Regional Transfer limit variation - Murraylink
There has been an unplanned outage of Murraylink.
The following constraint set was invoked at 1405 hrs 25/11/2024
I-ML_ZERO
The constraint set contains the following interconnector on the left hand side.
V-S-MNSP1
Refer to AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
Request for Generator Recall Information for the period 27/11/2024 for Region QLD
Refer to AEMO Electricity Market Notice no. 120895.
Please provide Generator Recall Information for the period from 27/11/2024, by 1500 hrs on 25/11/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.
SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf
Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf
AEMO Operations
Request for Generator Recall Information for the period 27/11/2024 for Region NSW
Refer to AEMO Electricity Market Notice no. 120894, and 120892.
Please provide Generator Recall Information for the period from 27/11/2024, by 1500 hrs on 25/11/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.
SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf
Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf
AEMO Operations
Inter-regional transfer limit variation - Directlink - NSW region - 22/11/2024
Inter-regional transfer limit variation - Directlink - NSW region - 22/11/2024
At 1911 hrs 22/11/2024 there was an unplanned outage of the No.2 leg of Directlink.
The following constraint set(s) invoked at 1920 hrs 22/11/2024
N-X_MBTE_2
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Directlink - NSW Region
Inter-Regional Transfer limit variation - Directlink - NSW Region
There has been an unplanned outage of the No 2 Leg of Directlink .
The following constraint set was invoked at 1720 hrs 22/11/2024
N-X_MBTE_2
The constraint set contains the following interconnector on the left hand side.
N-Q-MNSP1
Refer AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
Request for Generator Recall Information for the period from 25/11/2024 to 26/11/2024 for NSW Region
Refer to AEMO Electricity Market Notice no. 120700, 120699 and 120698.
Please provide Generator Recall Information for the period from 25/11/2024 to 26/11/2024, by 1200 hrs on 21/11/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.
SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf
Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf
AEMO Operations
Inter-regional transfer limit variation - Moorabool - Sydenham No. 2 500 kV Line - VIC region - 19/11/2024
Inter-regional transfer limit variation - Moorabool - Sydenham No. 2 500 kV Line - VIC region - 19/11/2024
A planned outage of Moorabool - Sydenham No. 2 500 kV Line in the VIC region was scheduled from 1130 hrs 13/11/2024 to 1900 hrs 20/11/2024.
The outage has been completed and Moorabool - Sydenham No. 2 500 kV Line returned to service at 1640 hrs 19/11/2024
Constraint set(s) revoked: V-MLSY_NOEMTT_R
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Southpine - Rocklea 809 275 kV Line - QLD region - 18/11/2024
Inter-regional transfer limit variation - Southpine - Rocklea 809 275 kV Line - QLD region - 18/11/2024
At 1545 hrs 18/11/2024 there was an unplanned outage of Southpine - Rocklea 809 275 kV Line.
The following constraint set(s) invoked at 1545 hrs 18/11/2024
Q-RLSP_809
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Armidale to Dumaresq (8C) 330 kV line - NSW region - 17/11/2024
Inter-regional transfer limit variation - Armidale to Dumaresq (8C) 330 kV line - NSW region - 17/11/2024
A planned outage of Armidale to Dumaresq (8C) 330 kV line in the NSW region was scheduled from 0500 hrs 17/11/2024 to 1700 hrs 17/11/2024.
The outage has been completed returned to service at 1330 hrs 17/11/2024
Constraint set(s) revoked:
N-ARDM_8C
N-DM_SVC
N-TW_SVC
N-X_8C+DM+TW_SVC
Manager NEM Real Time Operations