Market Notices

118304MARKET INTERVENTION17/09/2024 04:26:59 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer to Market Notice 118293

Direction is cancelled from: 1630 hrs 17/09/2024

Manager NEM Real Time Operations
     
118303MARKET INTERVENTION17/09/2024 04:01:12 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 118292

Direction is cancelled from: 1600 hrs 17/09/2024

Manager NEM Real Time Operations
     
118302MARKET INTERVENTION17/09/2024 12:18:20 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 118300

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2200 hrs 17/09/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1700 hrs 17/09/2024, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
118301INTER-REGIONAL TRANSFER17/09/2024 12:21:32 PM

Inter-regional transfer limit variation -South East to Tailem Bend No 1 275 KV Line - SA region - 17/09/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - South East to Tailem Bend No 1 275 KV Line - SA region - 17/09/2024

At 1034 hrs 17/09/2024 there was a short notice outage of South East to Tailem Bend No 1 275 KV Line.

The following constraint set(s) invoked at 1035 hrs 20/09/2024
S-TBSE,
S-BC_CP

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA,NSW1-QLD1,T-V-MNSP1,V-S-MNSP1,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
118300MARKET INTERVENTION17/09/2024 05:54:27 AM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2200 hrs 17/09/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
118299RESERVE NOTICE16/09/2024 07:16:21 PM

Cancellation of Actual (LOR1) condition in the NSW region - 16/09/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 16/09/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.118298 is cancelled at 1915 hrs 16/09/2024.

Manager NEM Real Time Operations
     
118298RESERVE NOTICE16/09/2024 06:16:31 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/09/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/09/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs

The capacity reserve requirement is 1400 MW
The minimum capacity reserve available is 1274 MW

Manager NEM Real Time Operations
     
118297RESERVE NOTICE16/09/2024 05:42:56 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1800 hrs 16/09/2024 to 1830 hrs 16/09/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1362 MW.

Manager NEM Real Time Operations
     
118296RESERVE NOTICE17/09/2024 01:13:10 PM

RESERVE NOTICE MT PASA PUBLICATION 17 September 2024

The MTPASA result published on 17 September 2024 identifies Low Reserve Conditions as annual unserved energy exceeds the Reliability Standard between:
-- September 2024 - September 2025 in South Australia.

AEMO declares low reserve conditions in accordance with clause 4.8.4 of the National Electricity Rules for the following region(s) and periods:
-- January 2025 - March 2025 in South Australia when forecast demand exceeds supply under some circumstances.

Please note that MTPASA informs the market of potential reliability issues to allow the market to respond in the first instance, potentially avoiding the need for any AEMO intervention.

For further information, please refer to:
https://www.aemo.com.au/Electricity/National-Electricity-Market-NEM/Data/Market-Management-System-MMS/Projected-Assessment-of-System-Adequacy

This notice supersedes Market Notice 118203 published on 10 September 2024.

Background
As part of a broader process of implementing the reliability standard, AEMO runs the Medium Term Projected Assessment of System Adequacy (MTPASA) process weekly to forecast expected unserved energy levels over a two year period. If the expected annual unserved energy exceeds the maximum level specified by the Reliability Standard, a Low Reserve Condition is identified.

For more information about how AEMO implements the reliability standard, please view the Reliability Standard Implementation Guidelines (RSIG) available on AEMO's website at https://www.aemo.com.au/Electricity/National

Forecasting
AEMO
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm