Timeline
-
Publication of the approach paper12 October 2022
-
Publication of the draft report3 March 2023
-
Publication of addendum to the draft report4 April 2023
-
Consultation on the draft report closes20 April 2023
-
Consultation on addendum to the draft report closes23 May 2023
-
Publication of Update Report Part 1 including draft NER amendments26 July 2023
-
Consultation closure on Update Report Part 123 August 2023
-
Publication of the final reportDecember 2023
-
Submission of Rule change proposals to AEMC04 April 2024
Key contact
Overview
AEMO has completed its first five-yearly review of the technical requirements for National Electricity Market (NEM) connection, in NER Schedules 5.2, 5.3 and 5.3a through its Access Standards Review (Review). The schedules set out technical requirements for connection of generation (and, from June 2024, integrated resource systems), loads and market network service facilities, respectively.
The three National Electricity Rules (NER) schedules set out the access standards that may be agreed for the connection of relevant plant to NEM transmission and distribution networks by registered participants and some other parties, to establish required levels of plant capability or performance in relation to specified technical requirements. For most requirements, access may be negotiated between an automatic access standard (AAS) and a minimum access standard (MAS). A number of requirements also specify negotiating parameters and general conditions to be met in all cases.
National Electricity Rules requirements
AEMO conducted the Review under NER 5.2.6A of the NER, to assess the need for amendment to the technical requirements. Under NER 5.2.6A(a), AEMO must conduct a review of some or all of the technical requirements in NER Schedules 5.2, 5.3 and 5.3a once in every five-year period to assess whether those requirements should be amended. NER 5.2.6A was introduced in October 2018, and this was the first review under that provision.
In conducting this review, among other things, AEMO is required to have regard to:
1. the national electricity objective
2. the need to achieve and maintain power system security
3. changes in power system conditions; and
4. changes in technology and capabilities of facilities and plant.
Outcomes
Final report
In December 2023, AEMO published a final report making recommendations to address 44 issues in NER Schedules 5.2, 5.3, and 5.3a. Final recommendations, if given effect through a rule amendment process, will realise a range of benefits including:
- aligning standards with best power system performance;
- improving power system resilience;
- streamlining the connections process; and
- accommodating new technology associated with large loads, grid-forming inverters, synchronous condensers, and HVDC links.
Rule change proposals
In April 2024, AEMO submitted two initial rule change proposals to the Australian Energy Market Commission (AEMC) requesting amendments to the NER giving effect to the final Review recommendations. AEMO requested the AEMC consider the fast-track process for preliminary rule changes arising from the Schedule 5.2 and 5.3a recommendations. A standard rule change process was sought to address other recommendations. Stakeholders are encouraged to get involved with the AEMC rule change process. AEMO rule change proposals and associated documentation can be accessed at the AEMC website: ·
Further reviews
AEMO has identified three areas for further review:
1. Load technical requirements - The Review has indicated that the technologies for very large load projects in hydrogen production, which are most likely to impact power system security, are experiencing a period of rapid development. This requires a more detailed understanding of their potential capabilities in close collaboration with developers. AEMO intends to use the Schedule 5.3 recommendations as a starting point to develop more detailed technical requirements suitable for a Rule change proposal submission in 2025.
2. Connection of grid-forming (GFM) technology – AEMO has focussed initial recommendations for GFM connections on amending relevant technical requirements to ensure they do not inadvertently hinder the connection of GFM technology. AEMO acknowledges the importance of further work to develop core requirements to support the connection of GFM technology, which requires a prudent level of validation and testing. The further work will leverage the outcomes of lessons learnt and knowledge sharing material developed through the ARENA funded grid forming initiative to develop more detailed technical requirements suitable for a Rule change proposal submission in 2025.
3. AEMO’s role in smaller connections – AEMO is not presently recommending a size threshold on AEMO advisory matters, largely based on feedback opposing the change. However, AEMO considers there to be value in examining this question further, to consider more broadly AEMO’s role in efficiently supporting NPSs on power system security matters related to both individual and cumulative impacts of smaller plant on the operation of the power system. The timing for this review is still to be decided.
Documents
-
Approach paper
-
Draft report
-
Draft Report Addendum
-
Update Report
-
Final report
-
03/03/2023
Draft report - AEMO review of technical requirements for connection under Schedules 5.2, 5.3 and 5.3a of the National Electricity Rules
1.65 MB -
03/03/2023
Stakeholder feedback template for Schedule 5.2 and 5.3a recommendations (optional completion)
60.5 KB -
14/04/2023
Presentation slides from 14 April 2023
1.09 MB
Written submissions from stakeholders on draft report (close 20 April 2023)
AEMO received 18 submissions on the technical requirements and recommendations in the primary draft report (that is relating to Schedules 5.2 and 5.3a).
Submissions were received from:
-
04/05/2023
AGL
120.21 KB -
04/05/2023
Amp Power
215.11 KB -
04/05/2023
APD
283.26 KB -
04/05/2023
AusNet
819.21 KB -
04/05/2023
Bo Yin
181.43 KB -
04/05/2023
CEC
657.13 KB -
04/05/2023
CPSA
189.05 KB -
04/05/2023
Energy Queensland
147.48 KB -
04/05/2023
Goldwind Australia
139.37 KB -
04/05/2023
Hitachi Energy
226.24 KB -
24/05/2023
Hydro Tasmania
217.14 KB -
04/05/2023
Marinus Link
346.13 KB -
04/05/2023
Rod Hughes Consulting
108.87 KB -
04/05/2023
TasNetworks
693.41 KB -
04/05/2023
Total Eren
192.65 KB -
04/05/2023
Transgrid
283.31 KB
Late submissions were received from:
Written submissions from stakeholders on addendum to draft report (close 23 May 2023)
AEMO received 11 submissions on the technical requirements and recommendations in the addendum to the draft report (that is relating to Schedule 5.3).
Submissions were received from:
A late submission was received from:
-
26/07/2023
Draft Recommendations Update Report – NER Schedules 5.2 & 5.3a
890.5 KB -
26/07/2023
Appendix A1. Stakeholder consultation analysis and revised recommendations
1.21 MB -
26/07/2023
Appendix A2. Draft NER amendments
2.68 MB -
26/07/2023
Stakeholder feedback template for Schedule 5.2 and 5.3a revised recommendations (optional completion)
63.74 KB
Written Submissions
-
06/09/2023
Amp Power Australia
211.71 KB -
06/09/2023
AusNet
525.22 KB -
06/09/2023
Bo Yin
206.09 KB -
06/09/2023
Catarpillar
210.53 KB -
06/09/2023
CEC
409.08 KB -
06/09/2023
CPSA
93.22 KB -
06/09/2023
CTLab
348.62 KB -
06/09/2023
ENA
134.66 KB -
06/09/2023
Energy Queensland
199.45 KB -
06/09/2023
Huawei Australia
209.38 KB -
06/09/2023
Hydro Tasmania
248.33 KB -
06/09/2023
NEOEN
232.36 KB -
06/09/2023
Powerlink
626.6 KB -
06/09/2023
Powerlink - Cover Letter
439.6 KB -
06/09/2023
SAPN
289.47 KB -
06/09/2023
Solar Turbines Sagl
293.77 KB