AEMO review of technical requirements for connection (NER clause 5.2.6A)

12/10/2022
Market National Electricity Market
StageSecond Stage
ConvenorAEMO NEM
Initiated12/10/2022
Accepting submissions?No
Submissions close23/08/2023

Timeline

  • Publication of the approach paper
    12 October 2022
  • Publication of the draft report
    3 March 2023
  • Publication of addendum to the draft report
    4 April 2023
  • Consultation on the draft report closes
    20 April 2023
  • Consultation on addendum to the draft report closes
    23 May 2023
  • Publication of Update Report Part 1 including draft NER amendments 
    26 July 2023
  • Consultation closure on Update Report Part 1
    23 August 2023
  • Publication of the final report
    December 2023

Key contact

A mail icon. Email: contact.connections@aemo.com.au

Overview

AEMO has completed its first five-yearly review of the technical requirements for National Electricity Market (NEM) connection, in NER Schedules 5.2, 5.3 and 5.3a through its Access Standards Review (Review). The schedules set out technical requirements for connection of generation (and, from June 2024, integrated resource systems), loads and market network service facilities, respectively.

The three National Electricity Rules (NER) schedules set out the access standards that may be agreed for the connection of relevant plant to NEM transmission and distribution networks by registered participants and some other parties, to establish required levels of plant capability or performance in relation to specified technical requirements. For most requirements, access may be negotiated between an automatic access standard (AAS) and a minimum access standard (MAS). A number of requirements also specify negotiating parameters and general conditions to be met in all cases.

National Electricity Rules requirements

AEMO conducted the Review under NER 5.2.6A of the NER, to assess the need for amendment to the technical requirements. Under NER 5.2.6A(a), AEMO must conduct a review of some or all of the technical requirements in NER Schedules 5.2, 5.3 and 5.3a once in every five-year period to assess whether those requirements should be amended. NER 5.2.6A was introduced in October 2018, and this was the first review under that provision.

In conducting this review, among other things, AEMO is required to have regard to:

1. the national electricity objective
2. the need to achieve and maintain power system security
3. changes in power system conditions; and
4. changes in technology and capabilities of facilities and plant.

Outcomes

The final report makes recommendations to address 44 issues in NER Schedules 5.2, 5.3 and 5.3a which were identified by AEMO and its stakeholders over the course of the Review. Stakeholders have included approximately 250 individuals across over 100 organisations representing Network Service Providers, Original Equipment Manufacturers (OEMs), developers and large load customers.

Final recommendations, once given effect through a subsequent NER amendment process, will realise a range review objectives, which include:

  • aligning standards with best power system performance;
  • improving power system resilience;
  • streamlining the connections process; and
  • accommodating new technology associated with large loads, grid-forming inverters, synchronous condensers and HVDC links.

Next steps

On publication of the final report, AEMO will write to the AEMC to confirm that AEMO intends to submit rule change proposals, and request the AEMC to consider the fast track process for the majority of its rule changes arising from the Schedule 5.2 and 5.3a recommendations. Other recommendations would then propose a standard rule change process seeking to make other final recommendations.

Engagement

Prior to the final report, AEMO published the following key documents in the Review:

  • An approach paper (published 12 October 2022) that described the matters that AEMO proposed to review.
  • A draft report (published 3 March 2023) setting out its draft recommendations for amendments to technical requirements of NER Schedules 5.2 and 5.3a, and the reasons for its recommendations. 18 stakeholders made submissions on this report.
  • An addendum to the draft report (published 4 April 2023) setting out its draft recommendations for amendments to technical requirements of NER Schedule 5.3, and the reasons for its recommendations. 11 stakeholders made submissions on this report
  • An update report (published 26 July 2023) setting out revised recommendations for amendments to technical requirements of NER Schedules 5.2 and 5.3a, the reasons for its recommendations, and initial proposed drafting of NER amendments that could give effect to the revised recommendations. 23 stakeholders made submissions on this report.

Stakeholder feedback on the above documents has informed AEMO’s final recommendations.

Engagement on Update Report

AEMO facilitated a public webinar forum on Wednesday 9 August 2023 to discuss the recommendations set out in its Update Report.

The webinar provided the:

  • current status of the Review;
  • an overview of revised recommendations of the Update Report; and t (Part 1)
  • the opportunity for stakeholders to raise questions or issues regarding the revised recommendations.

Engagement on Draft Report

AEMO facilitated a public webinar forum on Wednesday 12 April 2023 to discuss the recommendations set out in its Draft Report. The webinar provided was facilitated to provide background, approach and current status of the Review; overview of recommendations made by the draft report and addendum; and the opportunity for stakeholders to raise questions or issues regarding the draft recommendations.

Documents

  • Approach paper
  • Draft report
  • Draft Report Addendum
  • Update Report
  • Final report
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm