Revised testing time for Project Energy Connect (PEC-1) 6th November 2024 for flows in both directions
Refer to market notice 119901
The Project Energy Connect (PEC-1) testing opportunity has changed ans it is now on 6th November at 22:00 hrs.
The test is for flows in both directions up to 50 MW.
This test includes a trip and reclose of a line in South Australia.
Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.
Terry Liu
AEMO Operations
Cancellation of a Non-Credible Contingency Event: Tungatinah-Lake Echo-Waddamana 1 110kV line and Tungatinah-Waddamana 2 110kV line in TAS1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: TAS1
Lines: Tungatinah-Lake Echo-Waddamana 1 110kV and Tungatinah-Waddamana 2 110kV
Cancellation time: 06/11/2024 09:24
Constraint set(s) revoked:
T-TUWA12_110_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE
Refer AEMO Electricity Market Notice 119943
Auto-generated on behalf of Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region [beginning] on 06/11/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 119940 is cancelled at 0900 hrs 06/11/2024.
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Tungatinah-Lake Echo-Waddamana 1 110kV line and Tungatinah-Waddamana 2 110kV line in TAS1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: TAS1
Lines: Tungatinah-Lake Echo-Waddamana 1 110kV and Tungatinah-Waddamana 2 110kV
Duration: 06/11/2024 08:21 until further notice
Constraint set(s) invoked:
T-TUWA12_110_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 06/11/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1800 hrs 06/11/2024 to 1830 hrs 06/11/2024.
The forecast capacity reserve requirement is 1108 MW.
The minimum capacity reserve available is 1086 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 119927 has been updated at 0430 hrs to the following:
[1.] From 1800 hrs 06/11/2024 to 1830 hrs 06/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1312 MW.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 119931
The TORRB4 TORRENS ISLAN unit is now expected to synchronise at 0230 hrs 06/11/2024 direction is now expected to stay in place until 1700 hrs 06/11/2024.
The direction update is issued at 0105 hrs 06/11/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 119929
The TORRB4 TORRENS ISLAN unit is now expected to synchronise at 0200 hrs 06/11/2024 direction is now expected to stay in place until 1700 hrs 06/11/2024.
The direction update is issued at 2155 hrs 05/11/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 119924
The TORRB4 TORRENS ISLAN unit is now expected to synchronise at 2330 hrs 05/11/2024 direction is now expected to stay in place until 1700 hrs 06/11/2024.
The direction update is issued at 1855 hrs 05/11/2024.
Manager NEM Real Time Operations