[EventId:202408051700_review] Prices for interval 05-Aug-2024 17:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1655 hrs on 5 August 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 05-Aug-2024 17:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202408051655_review] Prices for interval 05-Aug-2024 16:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1650 hrs on 5 August 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 05-Aug-2024 16:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202408051650_review] Prices for interval 05-Aug-2024 16:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1645 hrs on 5 August 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 05-Aug-2024 16:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202408051645_review] Prices for interval 05-Aug-2024 16:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1640 hrs on 5 August 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 05-Aug-2024 16:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202408051640_review] Prices for interval 05-Aug-2024 16:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1635 hrs on 5 August 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 05-Aug-2024 16:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202408051635_review] Prices for interval 05-Aug-2024 16:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1630 hrs on 5 August 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 05-Aug-2024 16:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 05/08/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
[1.] From 1900 hrs 05/08/2024 to 2200 hrs 05/08/2024.
The forecast capacity reserve requirement is 450 MW.
The minimum capacity reserve available is 317 MW.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Keilor to Sth Morang 500kV Line - VIC region - 04/08/2024
Inter-regional transfer limit variation - Keilor to Sth Morang 500kV Line - VIC region - 04/08/2024
A planned outage of Keilor to Sth Morang 500kV Line in the VIC region was scheduled from 1000 hrs 04/08/2024 to 1300 hrs 04/08/2024.
The outage has been completed and Keilor to Sth Morang 500kV Line returned to service at 1050 hrs 04/08/2024
Constraint set(s) revoked: V-KTSM_R
Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: TAS1
Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown
Cancellation time: 04/08/2024 02:19
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 117543
Auto-generated on behalf of Manager NEM Real Time Operations