Direction - SA region to Synergen Power Pty Limited - MINTARO MINTARO GAS
Direction - SA region to Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer to Market Notice 119651
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Synergen Power Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS at 1600 hrs 30/10/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0700 hrs 31/10/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1730 hrs 31/10/2024 / further notice.
Synergen Power Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 119659
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 1/11/2024.
The direction update is issued at 1600 hrs 30/10/2024.
Manager NEM Real Time Operations
Forecast Minimum System Load 1 (MSL1) in the VIC Region on 05/11/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region on 05/11/2024.
Minimum regional demand is forecast to be 1238 MW at 1300 hrs, and the advisory threshold is:
MSL1 - 1535 MW
MSL2 - 1035 MW
MSL3 - 535 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1030 hrs to 1400 hrs 05/11/2024.
AEMO Operations
Cancellation - AEMO Intervention Event - SA region 25/10/2024
Cancellation - AEMO Intervention Event - SA region 25/10/2024
Refer to Market Notice 119414
The AEMO Intervention Event and all associated directions are cancelled from 1700 hrs on 29/10/2024.
Manager NEM Real Time Operations
Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS
Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer to Market Notice 119604
Direction is cancelled from: 1700 hrs 29/10/2024
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 119573
Direction is cancelled from: 1700 hrs 29/10/2024
Manager NEM Real Time Operations
Direction - SA region to Synergen Power Pty Limited - MINTARO MINTARO GAS
Direction - SA region to Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer to Market Notice 119651
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Synergen Power Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS at 1600 hrs 29/10/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0730 hrs 30/10/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1730 hrs 30/10/2024 / further notice.
Synergen Power Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 119651
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1600 hrs 29/10/2024
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0030 hrs 30/10/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 31/10/2024
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Direction - SA region 29/10/2024
Direction - SA region 29/10/2024
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1605 hrs on 29/10/2024.
Intervention pricing does not apply to this AEMO intervention event.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations