Filter by category
Filter by Date
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 24/10/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 119311 has been updated at 1750 hrs to the following:
[1.] From 1800 hrs 24/10/2024 to 1930 hrs 24/10/2024.
The forecast capacity reserve requirement is 1420 MW.
The minimum capacity reserve available is 1292 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 24/10/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 119263 is cancelled at 1650 hrs 24/10/2024.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - [outage element] - NSW region - 24/10/2024
Inter-regional transfer limit variation - [outage element] - NSW region - 24/10/2024
At 1435 hrs 24/10/2024 there was an unplanned outage of Directlink cable 1 and cable 3 (note cable 2 was on a prior outage).
The following constraint set(s) invoked at 1445 hrs 24/10/2024
N-X_MBTE_3
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 30/10/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following periods:
From 1830 hrs to 1900 hrs 30/10/2024.
The forecast capacity reserve requirement is 1130 MW.
The minimum capacity reserve available is 1120 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 29/10/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following periods:
From 1800 hrs to 1900 hrs 29/10/2024.
The forecast capacity reserve requirement is 1040 MW.
The minimum capacity reserve available is 995 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region 28/10/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following periods:
[1.] From 1730 hrs to 1800 hrs 28/10/2024.
The forecast capacity reserve requirement is 1044 MW.
The minimum capacity reserve available is 768 MW.
[2.] From 1900 hrs to 2030 hrs 28/10/2024.
The forecast capacity reserve requirement is 1052 MW.
The minimum capacity reserve available is 673 MW.
AEMO Operations
CHG0099241 | Completed | Production | Migrate DEV / TEST / Pre-Production (PPD) VLAN 104 Gateway in Norwest from the Old Core Switches to the New Core Switches.
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Local Area Network
Change Title: Migrate DEV / TEST / Pre-Production (PPD) VLAN 104 Gateway in Norwest from the Old Core Switches to the New Core Switches.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0099235 | Completed | Production | Migrate Pre-Production (PPD) VLAN 108 Gateway in Norwest from the Old Core Switches to the New Core Switches.
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Local Area Network
Change Title: Migrate Pre-Production (PPD) VLAN 108 Gateway in Norwest from the Old Core Switches to the New Core Switches.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 24/10/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 119211 has been updated at 1400 hrs to the following:
[1.] From 1800 hrs 24/10/2024 to 2030 hrs 24/10/2024.
The forecast capacity reserve requirement is 1420 MW.
The minimum capacity reserve available is 1209 MW.
Manager NEM Real Time Operations