Filter by category
Filter by Date
Non-credible contingency event - QLD region - 30/07/2024
Non-credible contingency event - QLD region - 30/07/2024
At 0537 hrs the Darling Downs Power Station GT1, GT3 and and the steam turbine tripped from 484 MW.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Update - Non-credible contingency event - QLD region - 27/07/2024
Update - Non-credible contingency event - QLD region - 27/07/2024
Refer AEMO Electricity Market Notice 117487
At 1702 hrs the H38 Goodna No. 2 275kV Bus and the H38 Goodna No. 1 275/132kV transformer was returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Correction - Non-credible contingency event - QLD region - 27/07/2024
Correction to Market Notice 117486
Non-credible contingency event - QLD region - 27/07/2024
At 0951 hrs the H38 Goodna No. 2 275kV Bus and the H38 Goodna No. 1 275/132kV transformer tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Non-credible contingency event - QLD region - 27/07/2024
Non-credible contingency event - QLD region - 27/07/2024
At 0951 hrs the H3 Goodna No. 2 275kV Bus and the H3 Goodna No. 1 275/132kV transformer tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
CHG0091533 | Production | Planned Outage for the Gas Short Term Trading Market Systems Production.
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Short Term Trading Market
Change Title: Planned Outage for the Gas Short Term Trading Market Systems Production.
Change Start Date & Time: 08/08/2024 09:00:00 AEST
Change End Date & Time: 08/08/2024 22:00:00 AEST
Outage Start Date & Time: 08/08/2024 18:30:00 AEST
Outage End Date & Time: 08/08/2024 21:00:00 AEST
Environment: Production
Participant Impact and Requirements: Gas Short Term Trading Market (STTM) services including SWEX and MIS, SPI and SBS will not be available during the outage window in Production.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
CHG0090458 | Completed | Production | Planned Maintenance to Brisbane Internet firewall.
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Internet Access
Change Title: Planned Maintenance to Brisbane Internet firewall.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0091275 | Completed | Production | MSATS - eMDM Maintenance AKS v1.28 upgrade
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: MSATS - eMDM Maintenance AKS v1.28 upgrade
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0090458 | Production | Planned Maintenance to Brisbane Internet firewall.
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Internet Access
Change Title: Planned Maintenance to Brisbane Internet firewall.
Change Start Date & Time: 20/07/2024 14:00:22 AEST
Change End Date & Time: 20/07/2024 17:00:22 AEST
Outage Start Date & Time: 20/07/2024 14:30:26 AEST
Outage End Date & Time: 20/07/2024 14:35:26 AEST
Environment: Production
Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned outage:
IPWAN Participants - Nil
Lan-2-Lan VPN Participants (IPSEC) - Nil
B2B VPN - May experience a short 5-10 second drop of VPN tunnel connectivity to Brisbane DC.
Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO NSW datacenter termination point prior to this scheduled outage.
SSL VPN Participants: Nil
GASHUB: Nil
Other Impacts will have been communicated in advance.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
CHG0091273 | Completed | Pre-Production | Pre-Prod MASTS - eMDM Maintenance AKS v1.28 upgrade
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MDM - Meter Data Management
Change Title: Pre-Prod MASTS - eMDM Maintenance AKS v1.28 upgrade
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.