Filter by category
Filter by Date
Update - Network Augmentation Commissioned - QLD Region - 09/04/2024
Update - Network Augmentation Commissioned - QLD Region - 09/04/2024
Refer Market notice: 115957
Guybal Munjan 275 kV Switching Station has been cut into the existing Ross - Chalumbin No.858 275 kV line to form the following circuits:
H93 Guybal Munjan - H32 Chalumbin No.858 275 kV line
H13 Ross - H93 Guybal Munjan No.8916 275 kV line
Manager NEM Real Time Operations
Network Augmentation Commissioned - QLD Region - 04/04/2024
Network Augmentation Commissioned - QLD Region - 04/04/2024
Commissioned:
H93 Guybal Munjan 275 kV Switching Station
H13 Ross - H93 Guybal Munjan No.8916 275 kV line
Manager NEM Real Time Operations
Non-credible contingency event - QLD region - 03/04/2024
Non-credible contingency event - QLD region - 03/04/2024
At 2322 hrs the Kareeya PS units 1, 2, 3 and 4 tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Update - Non-credible contingency event - NSW region - 03/04/2024
Update - Non-credible contingency event - NSW region - 03/04/2024
Refer AEMO Electricity Market Notice 115944
At 2301 hrs the Eraring Power Station Unit 1 and Unit 2 were returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Non-credible contingency event - NSW region - 03/04/2024
Non-credible contingency event - NSW region - 03/04/2024
At 1322 hrs the Eraring Power Station Unit 1 and the Eraring Power Station Unit 2 tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Non-credible contingency event - VIC region - 27/03/2024
Non-credible contingency event - VIC region - 27/03/2024
At 1736 hrs the Terang to Mortlake South 220 kV line opened at the Terang end only.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Non-credible contingency event - SA region - Torrens Island 27/03/2024
Non-credible contingency event - SA region - Torrens Island 27/03/2024
At 1529 hrs there was an unplanned outage of the following elements:
Torrens Island A 275 kV West Bus
Torrens Island AC3 275 kV CB
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Cancellation - Severe Space Weather Watch Notification 25/03/2024
Cancellation - Severe Space Weather Watch Notification 25/03/2024
Refer to MN 115774
The Australian Bureau of Meteorology's Space Weather forecasting centre has cancelled the following notification.
Severe space weather watch: A recent Coronal Mass Ejection associated with a solar flare is anticipated to impact the Earth within the next 48 hours.
Manager NEM Real Time Operations
Non-credible contingency event - SA region - Torrens Island 25/03/2024
Non-credible contingency event - SA region - Torrens Island 25/03/2024
At 1412 hrs there was an unplanned outage of the following elements:
Torrens Island BW3 275 kV CB
Torrens Island BC3 275 kV CB
Torrens Island - Lefevre 275 kV line
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations