114284RESERVE NOTICE05/02/2024 10:09:07 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 05/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 114279 has been updated at 2350 hrs to the following:


[1.] From 1330 hrs 05/02/2024 to 1500 hrs 05/02/2024.
The forecast capacity reserve requirement is 1360 MW.
The minimum capacity reserve available is 759 MW.

[2.] From 1800 hrs 05/02/2024 to 1930 hrs 05/02/2024.
The forecast capacity reserve requirement is 1360 MW.
The minimum capacity reserve available is 851 MW.


Manager NEM Real Time Operations
114282NON-CONFORMANCE05/02/2024 09:40:12 AM

NON-CONFORMANCE Region NSW1 Monday, 5 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Sunday, 4 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: SEBSF1
Duration: 04/02/2024 12:45 to 05/02/2024 09:40
Amount: 35 MW
Constraint: NC-N_SEBSF1

Auto-generated on behalf of Manager NEM Real Time Operations
114280NON-CONFORMANCE05/02/2024 08:30:18 AM

NON-CONFORMANCE Region QLD1 Monday, 5 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 5 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 05/02/2024 08:15 to 05/02/2024 08:30
Amount: -50 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
114279RESERVE NOTICE05/02/2024 07:26:31 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 05/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 114269 has been updated at 2350 hrs to the following:


[1.] From 1330 hrs 05/02/2024 to 1500 hrs 05/02/2024.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 894 MW.

[2.] From 1730 hrs 05/02/2024 to 1900 hrs 05/02/2024.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 780 MW.


Manager NEM Real Time Operations
114272RESERVE NOTICE04/02/2024 11:52:03 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 05/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 114269 has been updated at 2350 hrs to the following:

[1.] From 1400 hrs 05/02/2024 to 1900 hrs 05/02/2024.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 690 MW.


Manager NEM Real Time Operations
114270RESERVE NOTICE04/02/2024 11:01:54 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 05/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No.114250 has been updated at 2250 hrs to the following:

[1.] From 1800 hrs 05/02/2024 to 1900 hrs 05/02/2024.
The forecast capacity reserve requirement is 1263 MW.
The minimum capacity reserve available is 1039 MW.

Manager NEM Real Time Operations
114269RESERVE NOTICE04/02/2024 10:52:30 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 05/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 114248 has been updated at 2250 hrs to the following:

[1.] From 1400 hrs 05/02/2024 to 1630 hrs 05/02/2024.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 727 MW.

[2.] From 1700 hrs 05/02/2024 to 1900 hrs 05/02/2024.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 881 MW.

Manager NEM Real Time Operations
114264NON-CONFORMANCE04/02/2024 08:15:20 PM

NON-CONFORMANCE Region SA1 Sunday, 4 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Sunday, 4 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: QPS5
Duration: 04/02/2024 20:05 to 04/02/2024 20:15
Amount: 50 MW
Constraint: NC-S_QPS5

Auto-generated on behalf of Manager NEM Real Time Operations
114250RESERVE NOTICE04/02/2024 04:50:31 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 05/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:

[1.] From 1830 hrs 05/02/2024 to 1900 hrs 05/02/2024.
The forecast capacity reserve requirement is 1263 MW.
The minimum capacity reserve available is 1166 MW.


Manager NEM Real Time Operations