Update - Lightning vulnerable equipment in QLD region
Update - Lightning vulnerable equipment in QLD region
Special Reclassification of Transmission Equipment during lightning
Refer to AEMO Electricity Market Notice 112581 and 112884.
At 1424 hrs 21/12/2023, the Middle Ridge 275 kV circuit breakers 5432 and 5422 tripped. This offloaded the H14 Middle Ridge No.2 and No. 3 275/110 kV transformers
The cause of the trip was identified as due to lightning.
In accordance with SO_OP_3715, AEMO now considers the H14 Middle Ridge No. 2 and No. 3 275/110 kV transformers to be vulnerable due to lightning.
Manager NEM Real Time Operations
Update - Direction - SA Region - 27/12/2023
Update - Direction - SA Region - 27/12/2023
Refer Market Notice 112823
The AEMO intervention event that commenced from interval ending 1505 hrs on 27/12/2023 is continuing.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
Update - Direction - SA Region - 27/12/2023
Update - Direction - SA Region - 27/12/2023
Refer Market Notice 112823
The AEMO intervention event that commenced from interval ending 1505 hrs on 27/12/2023 is continuing.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
Cancellation of Minimum System Load 1 (MSL1) in the VIC Region on 31/12/2023
Cancellation - MSL1 - VIC Region
Refer Market Notice 112936
The MSL1 condition for 31/12/2023 is cancelled at 1600 hrs 31/12/2023
Manager NEM Real Time Operations
Minimum System Load 1 (MSL1) in the VIC Region on 31/12/2023
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1100 hrs 31/12/2023 to 1400 hrs 31/12/2023.
Minimum scheduled demand is forecast to be 1300 MW at 1300 hrs and the secure threshold for the forecast operating conditions is 2,000 MW.
AEMO is seeking a market response.
An insufficient market response may require AEMO to take action or intervene to maintain power system security in Victoria. This may result in action such as the direction of scheduled generation, curtailment of non-scheduled generation, and/or a direction to increase operational demand.
Manager NEM Real Time Operations
Update - Direction - SA Region - 27/12/2023
Update - Direction - SA Region - 27/12/2023
Refer Market Notice 112823
The AEMO intervention event that commenced from interval ending 1505 hrs on 27/12/2023 is continuing.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
Update - Direction - SA Region - 27/12/2023
Update - Direction - SA Region - 27/12/2023
Refer Market Notice 112823
The AEMO intervention event that commenced from interval ending 1505 hrs on 27/12/2023 is continuing.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
Update - Direction - SA Region - 27/12/2023
Update - Direction - SA Region - 27/12/2023
Refer Market Notice 112823
The AEMO intervention event that commenced from interval ending 1505 hrs on 27/12/2023 is continuing.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
Correction - Direction - SA region 27/12/2023
Correction - Direction - SA region 27/12/2023
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).
The direction was necessary to maintain the power system in a secure operating state.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1505 hrs on 27/12/2023.
Intervention pricing does not apply to this AEMO intervention event.
Manager NEM Real Time Operations