Increase to QNI limit to next hold point of 1400 MW Qld to NSW
Refer to market notices 117060.
AEMO, TransGrid, Powerlink have reviewed the test results following the QNI minor testing on 19th June 2024. The next hold point can now be released.
The hold point of 1400 MW from Qld to NSW will be implemented as of 1000 hrs 31st July 2024.
Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade
Ben Blake
AEMO Operations
CHG0091507 | Production | As part of the Platform Services Patching Program, webMethods Inactive Production Application Servers in Brisbane will have critical s
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Business to Business data exchange
Change Title: As part of the Platform Services Patching Program, webMethods Inactive Production Application Servers in Brisbane will have critical security patches applied.
Change Start Date & Time: 26/08/2024 08:00:00 AEST
Change End Date & Time: 28/08/2024 18:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: This is the Inactive Production environment, there is no impact for external participants.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?d=pp_services_status for any planned/unplanned maintenance activities .
Inter-regional transfer limit variation - Heywood - South East No 2 275 kV Line - SA region - 26/07/2024
Inter-regional transfer limit variation -Heywood - South East No 2 275 kV Line SA region - 26/07/2024
A planned outage of Heywood - South East No 2 275 kV Line in the SA region was scheduled from 0830 hrs 26/07/2024 to 1730 hrs 28/07/2024.
The outage has been extended until 1200 hrs 29/07/2024
Constraint set(s) invoked:
I-HYSE
I-VS_050
I-VS+LKB_050
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
CHG0091533 | Production | Planned Outage for the Gas Short Term Trading Market Systems Production.
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Short Term Trading Market
Change Title: Planned Outage for the Gas Short Term Trading Market Systems Production.
Change Start Date & Time: 08/08/2024 09:00:00 AEST
Change End Date & Time: 08/08/2024 22:00:00 AEST
Outage Start Date & Time: 08/08/2024 18:30:00 AEST
Outage End Date & Time: 08/08/2024 21:00:00 AEST
Environment: Production
Participant Impact and Requirements: Gas Short Term Trading Market (STTM) services including SWEX and MIS, SPI and SBS will not be available during the outage window in Production.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
Network Augmentation Commissioned - VIC Region - 30/07/2024
Network Augmentation Commissioned - VIC Region - 30/07/2024
Cressy Terminal Station has been cut into the existing Moorabool - Mortlake No.2 500 kV line to form the following circuits:
Cressy - Mortlake No.2 500 kV line
Cressy - Moorabool No.2 500 kV line
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Heywood M1 Transformer - VIC region - 25/07/2024
Inter-regional transfer limit variation - Heywood M1 Transformer - VIC region - 25/07/2024
A planned outage of Heywood M1 Transformer in the VIC region was scheduled from 0600 hrs 25/07/2024 to 1800 hrs 25/07/2024.
The outage has been completed and Heywood M1 Transformer returned to service at 1550 hrs 25/07/2024
Constraint set(s) revoked: V-HYTX_M12
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Keilor - Sth Morang 500kV Line - VIC region - 25/07/2024
Inter-regional transfer limit variation - Keilor - Sth Morang 500kV Line - VIC region - 25/07/2024
A planned outage of Keilor - Sth Morang 500kV Line ] in the VIC region was scheduled from 0700 hrs 25/07/2024 to 1630 hrs 25/07/2024.
The outage has been completed and Keilor - Sth Morang 500kV Line returned to service at 1450 hrs 25/07/2024
Constraint set(s) revoked: V-KTSM_R
Manager NEM Real Time Operations
CHG0090458 | Completed | Production | Planned Maintenance to Brisbane Internet firewall.
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Internet Access
Change Title: Planned Maintenance to Brisbane Internet firewall.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Inter-regional transfer limit variation - Heywood - South East 1 275 kV Line - SA region - 22/07/2024
Inter-regional transfer limit variation - Heywood - South East 1 275 kV Line - SA region - 22/07/2024
A planned outage of Heywood - South East 1 275 kV Line in the SA region was scheduled from 0930 hrs 22/07/2024 to 1700 hrs 22/07/2024.
The outage has been cancelled.
Constraint set(s) revoked:
I-HYSE
I-VS+LKB_050
I-VS_050
S-SECB6611_10
S-SE_1CP
Manager NEM Real Time Operations