Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer to Market Notice 118397
Direction is cancelled from: 1530 hrs 23/09/2024
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 23/09/2024
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 118396 has been updated at 1315 hrs to the following:
From 1930 hrs 23/09/2024 to 2100 hrs 23/09/2024.
The forecast capacity reserve requirement is 537 MW.
The minimum capacity reserve available is 443 MW.
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0000 hrs 24/09/2024.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 24/09/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:
From 1730 hrs 24/09/2024 to 2130 hrs 24/09/2024.
The forecast capacity reserve requirement is 600 MW.
The minimum capacity reserve available is 382 MW.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 118372
The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 1530 hrs 23/09/2024.
The direction update is issued at 1240 hrs 23/09/2024.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 23/09/2024
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 118395 has been updated at 1220 hrs to the following:
From 2000 hrs 23/09/2024 to 2030 hrs 23/09/2024.
The forecast capacity reserve requirement is 600 MW.
The minimum capacity reserve available is 552 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 23/09/2024
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 118392 has been updated at 1020 hrs to the following:
From 1830 hrs 23/09/2024 to 2200 hrs 23/09/2024.
The forecast capacity reserve requirement is 600 MW.
The minimum capacity reserve available is 450 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 23/09/2024
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 118374 has been updated at 0720 hrs to the following:
From 1800 hrs 23/09/2024 to 2230 hrs 23/09/2024.
The forecast capacity reserve requirement is 600 MW.
The minimum capacity reserve available is 523 MW.
Manager NEM Real Time Operations
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 118386
Direction is cancelled from: 0400 hrs 23/09/2024
Manager NEM Real Time Operations