Market Notices

119868RESERVE NOTICE04/11/2024 03:39:46 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 119827 has been updated at 1400 hrs 04/11/2024 to the following:

1. From 1630 hrs to 1730 hrs 07/11/2024.
The forecast capacity reserve requirement is 857 MW.
The minimum capacity reserve available is 470 MW.

2. From 1900 hrs to 2000 hrs 07/11/2024.
The forecast capacity reserve requirement is 978 MW.
The minimum capacity reserve available is 612 MW.

AEMO Operations
     
119863MARKET INTERVENTION04/11/2024 02:37:24 PM

Forecast Minimum System Load MSL1 condition in the VIC Region on 05/11/2024

AEMO ELECTRICITY MARKET NOTICE
Forecast Minimum System Load MSL1 condition in the VIC Region on 05/11/2024

Update to Market Notice 119743 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC on 05/11/2024.

Minimum regional demand is forecast to be 1258 MW at 1300 hrs, and the advisory threshold is:
MSL1 - 1320 MW
MSL2 - 820 MW
MSL3 - 320 MW

The regional demand is forecast to be below the MSL1 threshold for the following period[s]:
From 1200 hrs 05/11/2024 to 1330 hrs 05/11/2024.

Manager NEM Real Time Operations
     
119859MARKET INTERVENTION04/11/2024 01:49:57 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0700 hrs 05/11/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
119853RESERVE NOTICE04/11/2024 08:07:08 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 04/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 119834 has been updated at 0800 hrs to the following:

[1.] From 1730 hrs 04/11/2024 to 1930 hrs 04/11/2024.
The forecast capacity reserve requirement is 1120 MW.
The minimum capacity reserve available is 788 MW.

Manager NEM Real Time Operations
     
119848MARKET INTERVENTION04/11/2024 07:58:26 AM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.


Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 119835

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 1700 hrs 04/11/2024.

The direction update is issued at 0755 hrs 04/11/2024.

Manager NEM Real Time Operations
     
119847MARKET INTERVENTION04/11/2024 07:57:19 AM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 119836

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1630 hrs 04/11/2024.

The direction update is issued at 0755 hrs 04/11/2024.

Manager NEM Real Time Operations
     
119839RESERVE NOTICE03/11/2024 11:14:53 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 119829 has been updated at 2300 hrs 03/11/2024 to the following:

[1.] From 1500 hrs 07/11/2024 to 1930 hrs 07/11/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 885 MW.

Manager NEM Real Time Operations
     
119836MARKET INTERVENTION03/11/2024 09:13:13 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 119831

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1700 hrs 04/11/2024.

The direction update is issued at 2115 hrs 03/11/2024.

Manager NEM Real Time Operations
     
119835MARKET INTERVENTION03/11/2024 09:11:53 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.


Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 119832

The TORRB4 TORRENS ISLAN direction is now expected to start at 0900 hrs 04/11/2024.

The direction update is issued at 2115hrs 03/11/2024.

Manager NEM Real Time Operations
     