119191RESERVE NOTICE22/10/2024 03:11:06 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 24/10/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 119154 has been updated at 1400 hrs 22/10/2024 to the following:

1. From 0500 hrs to 0630 hrs 24/10/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1371 MW.

2. From 1730 hrs to 2359 hrs 24/10/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1361 MW.

AEMO Operations
     
119187MARKET SYSTEMS22/10/2024 01:31:16 PM

CHG0098837 | Completed | Pre-Production | EMMS-Pre-Production Bay transfer for Core switch Refresh

Change Number: CHG0098837

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: Electricity Market Management System_PreProd

Change Title: EMMS-Pre-Production Bay transfer for Core switch Refresh

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
119183MARKET SYSTEMS22/10/2024 10:55:02 AM

CHG0098524 | Cancelled | Pre-Production | Maintenance activities to be performed on the Gas Short Term Trading Market Systems Pre-Production

Change Number: CHG0098524

Notification issued to: Market Notice

Notification Type: Cancelled

Change Type: Normal

Service/ Component: Short Term Trading Market (STTM)

Change Title: Maintenance activities to be performed on the Gas Short Term Trading Market Systems Pre-Production.

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
     
119162RESERVE NOTICE21/10/2024 03:08:27 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 25/10/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 0000 hrs to 0400 hrs 25/10/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1342 MW.

AEMO Operations
     
119154RESERVE NOTICE21/10/2024 03:07:03 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 24/10/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

1. From 0430 hrs to 0630 hrs 24/10/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1338 MW.

2. From 1700 hrs to 2359 hrs 24/10/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1324 MW.

AEMO Operations
     
119153RESERVE NOTICE21/10/2024 03:05:37 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 24/10/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

From 1730 hrs to 1900 hrs 24/10/2024.
The forecast capacity reserve requirement is 1193 MW.
The minimum capacity reserve available is 1090 MW.

AEMO Operations
     
119139MARKET SYSTEMS21/10/2024 09:22:19 AM

CHG0098496 | Completed | Production | QLD Marketnet Router Replacement

Change Number: CHG0098496

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: Market Network

Change Title: QLD Marketnet Router Replacement

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
119137MARKET SYSTEMS21/10/2024 08:20:38 AM

CHG0098837 | Pre-Production | EMMS-Pre-Production Bay transfer for Core switch Refresh

Change Number: CHG0098837

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Electricity Market Management System_PreProd

Change Title: EMMS-Pre-Production Bay transfer for Core switch Refresh

Change Start Date & Time: 22/10/2024 07:00:00 AEST
Change End Date & Time: 22/10/2024 19:30:00 AEST
Outage Start Date & Time:
Outage End Date & Time:

Environment: Pre-Production

Participant Impact and Requirements: A Bay transfer is scheduled for 22nd October is not expected to have any impact. If any issues are identified because of this maintenance activity, please contact the AEMO Support Hub 1300 236 600.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
     
119055RESERVE NOTICE19/10/2024 11:10:41 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region [beginning] on 19/10/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 119023 is cancelled at 1100 hrs 19/10/2024.

Manager NEM Real Time Operations
     