118998INTER-REGIONAL TRANSFER17/10/2024 07:20:04 PM

Inter-regional transfer limit variation - Brinkworth- Red Hill- Bungama 132kV lines - SA region - 17/10/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Brinkworth- Red Hill- Bungama 132kV lines - SA region - 17/10/2024

At 1846 hrs 17/10/2024 there was an unplanned outage of Brinkworth- Red Hill- Bungama 132kV lines.

The following constraint set(s) invoked at 1855 hrs 17/10/2024
S-BRBG

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
118997INTER-REGIONAL TRANSFER17/10/2024 07:18:47 PM

Inter-regional transfer limit variation - Hummocks - Bungama 132kV line - SA region - 17/10/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Hummocks - Bungama 132kV line - SA region - 17/10/2024

At 1842 hrs 17/10/2024 there was an unplanned outage of Hummocks - Bungama 132kV line.

The following constraint set(s) invoked at 1850 hrs 17/10/2024
S-HUBG

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
118996INTER-REGIONAL TRANSFER17/10/2024 07:13:32 PM

Inter-regional transfer limit variation - Blyth West - Munno Para 275kV line- SA region - 17/10/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Blyth West - Munno Para 275kV line - SA region - 17/10/2024

At 1848 hrs 17/10/2024 there was an unplanned outage of Blyth West - Munno Para 275kV line.

The following constraint set(s) invoked at 1855 hrs 17/10/2024
S-BWMP

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
118873RESERVE NOTICE14/10/2024 12:55:45 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/10/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 118869 is cancelled at 1100 hrs 14/10/2024.

No LOR2 condition is currently forecast in the STPASA period.

AEMO Operations
     
118869RESERVE NOTICE14/10/2024 10:59:46 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/10/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1730 hrs to 1930 hrs 16/10/2024.
The forecast capacity reserve requirement is 1456 MW.
The minimum capacity reserve available is 1407 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
118736INTER-REGIONAL TRANSFER09/10/2024 07:58:20 PM

Inter-regional transfer limit variation - Moorabool to Sydenham 500 kV No.2 line - VIC region - 09/10/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Moorabool to Sydenham 500 kV No.2 line - VIC region - 09/10/2024

A planned outage of Moorabool to Sydenham 500 kV No.2 line in the VIC region was scheduled from 0600 hrs 01/10/2024 to 2030 hrs 11/10/2024.

The outage has been completed and Moorabool to Sydenham 500 kV No.2 line returned to service at 1940 hrs 09/10/2024

Constraint set(s) revoked: V-MLSY_NOEMTT_R

Manager NEM Real Time Operations
     
118647RESERVE NOTICE07/10/2024 02:30:03 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 08/10/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 118644 is cancelled at 1415 hrs 07/10/2024.

Manager NEM Real Time Operations
     
118644RESERVE NOTICE07/10/2024 01:21:49 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 08/10/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Periods:

[1.] From 1530 hrs 08/10/2024 to 1600 hrs 08/10/2024.
The forecast capacity reserve requirement is 719 MW.
The minimum capacity reserve available is 615 MW.

[2.] From 1730 hrs 08/10/2024 to 1900 hrs 08/10/2024.
The forecast capacity reserve requirement is 692 MW.
The minimum capacity reserve available is 475 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
     
118639RESERVE NOTICE07/10/2024 10:45:14 AM

STPASA - Update to the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 08/10/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 118637 has been updated at 1000 hrs 07/10/2024 to the following:

[1.] From 1530 hrs 1600 hrs 08/10/2024.
The forecast capacity reserve requirement is 783 MW.
The minimum capacity reserve available is 608 MW.

[2.] From 1730 hrs to 1930 hrs 08/10/2024.
The forecast capacity reserve requirement is 755 MW.
The minimum capacity reserve available is 467 MW.


AEMO is seeking a market response.

AEMO Operations.
     