Filter by category
Filter by Date
[EventId:202411010835_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 01 November 2024 08:35
Issued by Australian Energy Market Operator Ltd at 0835 hrs on 1 November 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 1 November 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0835 hrs on 1 November 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region [beginning] on 31/10/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 119693 is cancelled at 1720 hrs 31/10/2024.
Manager NEM Real Time Operations
[EventId:202410311700_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 31 October 2024 17:00
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 31 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 31 October 2024.
Refer to market notice: 119705
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1700 hrs on 31 October 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202410311535_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 31 October 2024 15:35
Issued by Australian Energy Market Operator Ltd at 1535 hrs on 31 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 31 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1535 hrs on 31 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/11/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1630 hrs to 1900 hrs 07/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1014 MW.
AEMO Operations
NON-CONFORMANCE Region NSW1 Thursday, 31 October 2024
NON-CONFORMANCE Region NSW1 Thursday, 31 October 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:.
Unit: MP1
Duration: 31/10/2024 13:25 to 31/10/2024 13:30
Amount: -52 MW
Constraint: NC-N_MP1
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Thursday, 31 October 2024
NON-CONFORMANCE QLD1 Region Thursday, 31 October 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 31/10/2024 12:50 to 31/10/2024 13:05
Amount: 24 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 31/10/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 119692 has been updated at 0945 hrs to the following:
[1.] From 1730 hrs 31/10/2024 to 2000 hrs 31/10/2024.
The forecast capacity reserve requirement is 1292 MW.
The minimum capacity reserve available is 925 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 31/10/2024
[1.] From 1830 hrs 31/10/2024 to 1900 hrs 31/10/2024.
The forecast capacity reserve requirement is 1285 MW.
The minimum capacity reserve available is 1248 MW.
Manager NEM Real Time Operations