Update - Non-credible contingency event - NSW region - 31/10/2024
Update - Non-credible contingency event - NSW region - 31/10/2024
Refer AEMO Electricity Market Notice 119689
At 0345 hrs the Wagga B 330 kV bus was returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Non-credible contingency event - NSW region - 31/10/2024
Non-credible contingency event - NSW region - 31/10/2024
At 0028 hrs the Wagga B 330 kV bus tripped which offloaded the Wagga - Walla Walla SF 6Y 330 kV line and Wagga No.3 transformer.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
[EventId:202410301335_confirmed] Prices for interval 30-Oct-2024 13:35 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1355 hrs on 30 October 2024
PRICES ARE NOW CONFIRMED for trading interval 30-Oct-2024 13:35.
In accordance with Market Notice 119671 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202410301355_confirmed] Prices for interval 30-Oct-2024 13:55 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1355 hrs on 30 October 2024
PRICES ARE NOW CONFIRMED for trading interval 30-Oct-2024 13:55.
In accordance with Market Notice 119675 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202410301350_confirmed] Prices for interval 30-Oct-2024 13:50 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1355 hrs on 30 October 2024
PRICES ARE NOW CONFIRMED for trading interval 30-Oct-2024 13:50.
In accordance with Market Notice 119674 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202410301345_confirmed] Prices for interval 30-Oct-2024 13:45 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1355 hrs on 30 October 2024
PRICES ARE NOW CONFIRMED for trading interval 30-Oct-2024 13:45.
In accordance with Market Notice 119673 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202410301340_confirmed] Prices for interval 30-Oct-2024 13:40 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1355 hrs on 30 October 2024
PRICES ARE NOW CONFIRMED for trading interval 30-Oct-2024 13:40.
In accordance with Market Notice 119672 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202410301330_confirmed] Prices for interval 30-Oct-2024 13:30 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1355 hrs on 30 October 2024
PRICES ARE NOW CONFIRMED for trading interval 30-Oct-2024 13:30.
In accordance with Market Notice 119670 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
Update - Lightning vulnerable lines in Vic region
Update - Lightning vulnerable lines in Vic region
Refer to AEMO Electricity Market Notice 119029
At 1525 hrs on 18/10/2024 the Rowville - Yallourn No. 7 220 kV Line and the Rowville - Yallourn No. 8 220 kV Line tripped and auto-reclosed.
The cause of the trip was identified as due to Lightning.
In accordance with SO_OP_3715, AEMO now considers the Rowville - Yallourn No. 7 220 kV Line and the Rowville - Yallourn No. 8 220 kV Line to be vulnerable with a category of probable due to Lightning.
Manager NEM Real Time Operations