NON-CONFORMANCE Region QLD1 Friday, 26 January 2024
NON-CONFORMANCE QLD1 Region Friday, 26 January 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 26/01/2024 08:05 to 26/01/2024 08:15
Amount: -39 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
Update - Direction - SA Region - 24/01/2024
Update - Direction - SA Region - 24/01/2024
Refer Market Notice 113710
The AEMO intervention event that commenced from interval ending 1635 hrs on 24/01/2024 is continuing.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Thursday, 25 January 2024
NON-CONFORMANCE NSW1 Region Thursday, 25 January 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: ER01
Duration: 25/01/2024 11:40 to 25/01/2024 11:45
Amount: -81 MW
Constraint: NC-N_ER01
Auto-generated on behalf of Manager NEM Real Time Operations
Direction - SA region 24/01/2024
Direction - SA region 24/01/2024
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).
The direction was necessary to maintain the power system in a secure operating state.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1635 hrs on 24/01/2024.
Intervention pricing does not apply to this AEMO intervention event.
Manager NEM Real Time Operations
Update - Possible intervention to manage power system security in SA region
Update - Possible intervention to manage power system security in SA region
Refer AEMO Electricity Market Notice 113695
The synchronous generating units currently expected to be synchronised in SA from 0900 hrs 25/01/2024 will be inadequate to maintain a secure operating state in SA .
AEMO estimates that, in the absence of sufficient market response by 1630 hrs 24/01/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
Possible intervention to manage power system security in SA Region
Possible intervention to manage power system security in SA Region
The synchronous generating units currently expected to be synchronised in SA from 0000 hrs 26/01/2024 will be inadequate to maintain a secure operating state in SA.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
Update - Non-credible contingency event - QLD region - 23/01/2024
Update - Non-credible contingency event - QLD region - 23/01/2024
Refer AEMO Electricity Market Notice 113659
At 1122 hrs the H35 Strathmore No2 275 kV bus was returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
Nebo - Strathmore 878 275 kV line to remain out of service.
See Network Outage Scheduler (NOS) for further details.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Non-credible contingency event - QLD region - 23/01/2024
Non-credible contingency event - QLD region - 23/01/2024
At 0957 hrs the Strathmore No 2 275 kV bus tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
The following constraint set(s) invoked
Q-NESTM
Q-X_NQ_275_FDR+BUS
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Hazelwood - South Morang No2 500 kV Line - VIC region - 23/01/2024
Inter-regional transfer limit variation - Hazelwood - South Morang No2 500 kV Line - VIC region - 23/01/2024
At 0318 hrs 23/01/2024 there was an unplanned outage of Hazelwood - South Morang No2 500 kV Line.
The following constraint set(s) invoked at 0325 hrs 23/01/2024
V-HWSM
This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1,V-S-MNSP1,V-SA,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations