Market Notices

116345NON-CONFORMANCE26/04/2024 10:45:22 PM

NON-CONFORMANCE Region VIC1 Friday, 26 April 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Friday, 26 April 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: YWPS3
Duration: 26/04/2024 22:40 to 26/04/2024 22:45
Amount: 17 MW
Constraint: NC-V_YWPS3

Auto-generated on behalf of Manager NEM Real Time Operations
116329GENERAL NOTICE25/04/2024 11:56:40 AM

Planned outage of Gordon - Chapel St No. 1 220 kV line in the TAS region on 26/04/2024

AEMO ELECTRICITY MARKET NOTICE

The Gordon - Chapel St No. 1 220 kV line in the Tasmania (TAS) region is planned to be out of service from 1030 hrs on 26/04/2024 to 1500 hrs on 26/04/2024

A credible contingency event during this planned outage could cause a large reduction in generation in TAS.

Refer AEMO Network Outage Schedule (NOS) for further details.

Manager NEM Real Time Operations
116322PRICES SUBJECT TO REVIEW24/04/2024 05:30:17 PM

[EventId:202404241735_review] Prices for interval 24-Apr-2024 17:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1730 hrs on 24 April 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 24-Apr-2024 17:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
116321PRICES SUBJECT TO REVIEW24/04/2024 05:25:19 PM

[EventId:202404241730_review] Prices for interval 24-Apr-2024 17:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1725 hrs on 24 April 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 24-Apr-2024 17:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
116320PRICES SUBJECT TO REVIEW24/04/2024 05:20:15 PM

[EventId:202404241725_review] Prices for interval 24-Apr-2024 17:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1720 hrs on 24 April 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 24-Apr-2024 17:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
116319PRICES SUBJECT TO REVIEW24/04/2024 05:15:22 PM

[EventId:202404241720_review] Prices for interval 24-Apr-2024 17:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1715 hrs on 24 April 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 24-Apr-2024 17:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
116318PRICES SUBJECT TO REVIEW24/04/2024 05:10:21 PM

[EventId:202404241715_review] Prices for interval 24-Apr-2024 17:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1710 hrs on 24 April 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 24-Apr-2024 17:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
116317PRICES SUBJECT TO REVIEW24/04/2024 05:05:24 PM

[EventId:202404241710_review] Prices for interval 24-Apr-2024 17:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1705 hrs on 24 April 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 24-Apr-2024 17:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
116307PRICES SUBJECT TO REVIEW24/04/2024 02:00:19 PM

[EventId:202404241405_review] Prices for interval 24-Apr-2024 14:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1400 hrs on 24 April 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 24-Apr-2024 14:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm