STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 27/01/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1530 hrs to 2130 hrs 27/01/2024.
The forecast capacity reserve requirement is 1188 MW.
The minimum capacity reserve available is 966 MW.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 25/01/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 113603 has been updated at 1400 hrs 23/01/2024 to the following:
From 1700 hrs to 2030 hrs 25/01/2024.
The forecast capacity reserve requirement is 1241 MW.
The minimum capacity reserve available is 737 MW.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 25/01/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 113607 has been updated at 1400 hrs 23/01/2024 to the following:
From 2100 hrs to 2130 hrs 25/01/2024.
The forecast capacity reserve requirement is 1735 MW.
The minimum capacity reserve available is 1332 MW.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 26/01/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 113609 has been updated at 1400 hrs 23/01/2024 to the following:
From 1700 hrs to 2030 hrs 26/01/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1240 MW.
AEMO Operations
Inter-regional transfer limit variation - Hazelwood - South Morang No2 500 kV Line - VIC region - 23/01/2024
Inter-regional transfer limit variation - Hazelwood - South Morang No2 500 kV Line - VIC region - 23/01/2024
At 0318 hrs 23/01/2024 there was an unplanned outage of Hazelwood - South Morang No2 500 kV Line.
The following constraint set(s) invoked at 0325 hrs 23/01/2024
V-HWSM
This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1,V-S-MNSP1,V-SA,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
[EventId:202401222005_review] Prices for interval 22-Jan-2024 20:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 2000 hrs on 22 January 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 22-Jan-2024 20:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202401222000_review] Prices for interval 22-Jan-2024 20:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1955 hrs on 22 January 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 22-Jan-2024 20:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202401221955_review] Prices for interval 22-Jan-2024 19:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1950 hrs on 22 January 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 22-Jan-2024 19:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202401221950_review] Prices for interval 22-Jan-2024 19:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1945 hrs on 22 January 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 22-Jan-2024 19:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.