PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region [beginning] on 09/10/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 118694 is cancelled at 1050 hrs 09/10/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 09/10/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1800 hrs 09/10/2024 to 1830 hrs 09/10/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1393 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 09/10/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 118671 is cancelled at 1630 hrs 08/10/2024.
Manager NEM Real Time Operations
Managing outages that create a credible risk of SA islanding
From 9th Oct 2024 AEMO will change constraints used during outages that create a credible risk of SA islanding.
From this date AEMO will:
1) Increase the maximum allowable flow on the V-SA interconnector from 50 MW to 250 MW in the VIC to SA direction, where the transmission outages is a planned outage.
2) Operate the SA region to the default 49-51 Hz target frequency containment band following a contingency event resulting in actual SA islanding. In order to meet this requirement, AEMO may now procure Contingency Raise FCAS locally from the SA region during these outages.
These changes reflect updated advice received by AEMO from the SA Jurisdictional System Security Coordinator.
The first network outage affected by this change is planned for 14th October 2024.
Andrew Groom
AEMO Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 09/10/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1730 hrs 09/10/2024 to 1930 hrs 09/10/2024.
The forecast capacity reserve requirement is 1144 MW.
The minimum capacity reserve available is 951 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/10/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 118665 is cancelled at 0555 hrs 08/10/2024.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/10/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 118664 has been updated at 2300 hrs to the following:
[1.] From 1730 hrs 08/10/2024 to 1900 hrs 08/10/2024.
The forecast capacity reserve requirement is 1198 MW.
The minimum capacity reserve available is 1045 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/10/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 118648 has been updated at 2130 hrs to the following:
[1.] From 1730 hrs 08/10/2024 to 1930 hrs 08/10/2024.
The forecast capacity reserve requirement is 1187 MW.
The minimum capacity reserve available is 863 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/10/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 118642 has been updated at 1430 hrs to the following:
[1.] From 1730 hrs 08/10/2024 to 1900 hrs 08/10/2024.
The forecast capacity reserve requirement is 1166 MW.
The minimum capacity reserve available is 1005 MW.