[EventId:202411041135_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 04 November 2024 11:35
Issued by Australian Energy Market Operator Ltd at 1135 hrs on 4 November 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 4 November 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1135 hrs on 4 November 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 04/11/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 119834 has been updated at 0800 hrs to the following:
[1.] From 1730 hrs 04/11/2024 to 1930 hrs 04/11/2024.
The forecast capacity reserve requirement is 1120 MW.
The minimum capacity reserve available is 788 MW.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 119835
The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 1700 hrs 04/11/2024.
The direction update is issued at 0755 hrs 04/11/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 119836
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1630 hrs 04/11/2024.
The direction update is issued at 0755 hrs 04/11/2024.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 119829 has been updated at 2300 hrs 03/11/2024 to the following:
[1.] From 1500 hrs 07/11/2024 to 1930 hrs 07/11/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 885 MW.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 119831
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1700 hrs 04/11/2024.
The direction update is issued at 2115 hrs 03/11/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 119832
The TORRB4 TORRENS ISLAN direction is now expected to start at 0900 hrs 04/11/2024.
The direction update is issued at 2115hrs 03/11/2024.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 04/11/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 119824 has been updated at 1630 hrs to the following:
[1.] From 1800 hrs 04/11/2024 to 1900 hrs 04/11/2024.
The forecast capacity reserve requirement is 1120 MW.
The minimum capacity reserve available is 937 MW.
Manager NEM Real Time Operations
Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS
Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer to Market Notice 119823
Direction is cancelled from: 2030 hrs 03/11/2024
Manager NEM Real Time Operations