Filter by category
Filter by Date
[EventId:202406251345_review] Prices for interval 25-Jun-2024 13:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1340 hrs on 25 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 25-Jun-2024 13:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202406251340_review] Prices for interval 25-Jun-2024 13:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1340 hrs on 25 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 25-Jun-2024 13:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202406251335_review] Prices for interval 25-Jun-2024 13:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1340 hrs on 25 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 25-Jun-2024 13:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202406251330_review] Prices for interval 25-Jun-2024 13:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1340 hrs on 25 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 25-Jun-2024 13:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
CHG0090919 | Pre-Production | Maintenance activities to be performed on the Gas Short Term Trading Market Systems Pre-Production.
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Short Term Trading Market (STTM)
Change Title: Maintenance activities to be performed on the Gas Short Term Trading Market Systems Pre-Production.
Change Start Date & Time: 27/06/2024 08:00:00 AEST
Change End Date & Time: 27/06/2024 17:30:00 AEST
Outage Start Date & Time: 27/06/2024 09:00:00 AEST
Outage End Date & Time: 27/06/2024 13:30:00 AEST
Environment: Pre-Production
Participant Impact and Requirements:
This is a regular procedure to allow routine maintenance. Short service outages over the day for STTM services including SWEX and MIS.
Pre-Production Gas Short Term Trading Market (STTM)
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
Non-credible contingency event - NSW region - 25/06/2024
Non-credible contingency event - NSW region - 25/06/2024
At 0901 hrs the Sydney West No.1 330 kV SVC tripped during switching for planned outage of Sydney West No.4 330/132 kV transformer.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Tuesday, 25 June 2024
NON-CONFORMANCE QLD1 Region Tuesday, 25 June 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 25/06/2024 09:35 to 25/06/2024 09:50
Amount: -40 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Monday, 24 June 2024
NON-CONFORMANCE QLD1 Region Monday, 24 June 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 24/06/2024 18:30 to 24/06/2024 20:20
Amount: 49 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Monday, 24 June 2024
NON-CONFORMANCE QLD1 Region Monday, 24 June 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 24/06/2024 19:30 to 24/06/2024 20:20
Amount: -42 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations