Market Notices

113700MARKET INTERVENTION24/01/2024 02:41:12 PM

Update - Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Possible intervention to manage power system security in SA region

Refer AEMO Electricity Market Notice 113695

The synchronous generating units currently expected to be synchronised in SA from 0900 hrs 25/01/2024 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 1630 hrs 24/01/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
113695MARKET INTERVENTION24/01/2024 12:39:07 PM

Possible intervention to manage power system security in SA Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA Region

The synchronous generating units currently expected to be synchronised in SA from 0000 hrs 26/01/2024 will be inadequate to maintain a secure operating state in SA.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
113662POWER SYSTEM EVENTS23/01/2024 11:31:54 AM

Update - Non-credible contingency event - QLD region - 23/01/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - QLD region - 23/01/2024

Refer AEMO Electricity Market Notice 113659

At 1122 hrs the H35 Strathmore No2 275 kV bus was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

Nebo - Strathmore 878 275 kV line to remain out of service.

See Network Outage Scheduler (NOS) for further details.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
113659POWER SYSTEM EVENTS23/01/2024 10:20:24 AM

Non-credible contingency event - QLD region - 23/01/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 23/01/2024

At 0957 hrs the Strathmore No 2 275 kV bus tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.
The following constraint set(s) invoked
Q-NESTM
Q-X_NQ_275_FDR+BUS

Manager NEM Real Time Operations
113654INTER-REGIONAL TRANSFER23/01/2024 03:30:39 AM

Inter-regional transfer limit variation - Hazelwood - South Morang No2 500 kV Line - VIC region - 23/01/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Hazelwood - South Morang No2 500 kV Line - VIC region - 23/01/2024

At 0318 hrs 23/01/2024 there was an unplanned outage of Hazelwood - South Morang No2 500 kV Line.

The following constraint set(s) invoked at 0325 hrs 23/01/2024
V-HWSM

This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1,V-S-MNSP1,V-SA,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
113653MARKET INTERVENTION23/01/2024 03:54:22 AM

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 19/01/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 19/01/2024

Refer Market Notice 113483

The AEMO Intervention Event and all associated directions are cancelled from 0400 hrs 23/01/2024

Manager NEM Real Time Operations
113649PRICES UNCHANGED22/01/2024 08:10:08 PM

[EventId:202401221945_confirmed] Prices for interval 22-Jan-2024 19:45 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2005 hrs on 22 January 2024

PRICES ARE NOW CONFIRMED for trading interval 22-Jan-2024 19:45.

In accordance with Market Notice 113639 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
113648PRICES UNCHANGED22/01/2024 08:09:10 PM

[EventId:202401222005_confirmed] Prices for interval 22-Jan-2024 20:05 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2005 hrs on 22 January 2024

PRICES ARE NOW CONFIRMED for trading interval 22-Jan-2024 20:05.

In accordance with Market Notice 113643 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
113647PRICES UNCHANGED22/01/2024 08:08:18 PM

[EventId:202401222000_confirmed] Prices for interval 22-Jan-2024 20:00 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2005 hrs on 22 January 2024

PRICES ARE NOW CONFIRMED for trading interval 22-Jan-2024 20:00.

In accordance with Market Notice 113642 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm