115204RESERVE NOTICE27/02/2024 10:58:37 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 115201 has been updated at 1000 hrs 27/02/2024 to the following:

From 1430 hrs 29/02/2024 to 2130 hrs 29/02/2024.
The forecast capacity reserve requirement is 1341 MW.
The minimum capacity reserve available is 0 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
115203RESERVE NOTICE27/02/2024 10:57:33 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

From 1730 hrs to 2000 hrs 29/02/2024.
The forecast capacity reserve requirement is 745 MW.
The minimum capacity reserve available is 336 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
115201RESERVE NOTICE27/02/2024 10:17:34 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 115197 has been updated at 0900 hrs 27/02/2024 to the following:

From 1430 hrs to 2100 hrs 29/02/2024.
The forecast capacity reserve requirement is 1329 MW.
The minimum capacity reserve available is 364 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
115197RESERVE NOTICE27/02/2024 08:49:08 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 115193 has been updated at 0800 hrs 27/02/2024 to the following:

From 1430 hrs to 2100 hrs 29/02/2024.
The forecast capacity reserve requirement is 1316 MW.
The minimum capacity reserve available is 16 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
115193RESERVE NOTICE27/02/2024 08:02:34 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 115190 has been updated at 0700 hrs 27/02/2024 to the following:

From 1500 hrs to 2100 hrs 29/02/2024.
The forecast capacity reserve requirement is 1318 MW.
The minimum capacity reserve available is 264 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
115192RESERVE NOTICE27/02/2024 08:01:29 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 115191 is cancelled at 0700 hrs 27/02/2024.

AEMO Operations
115191RESERVE NOTICE27/02/2024 04:41:18 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 115183 has been updated at 0440 hrs 27/02/2024 to the following:

[1.] From 1730 hrs 29/02/2024 to 2000 hrs 29/02/2024.
The forecast capacity reserve requirement is 729 MW.
The minimum capacity reserve available is 364 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
115190RESERVE NOTICE27/02/2024 04:40:17 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 115181 has been updated at 0440 hrs 27/02/2024 to the following:

[1.] From 1500 hrs 29/02/2024 to 2000 hrs 29/02/2024.
The forecast capacity reserve requirement is 1250 MW.
The minimum capacity reserve available is 272 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
115183RESERVE NOTICE26/02/2024 09:48:57 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 115153 has been updated at 2145 hrs 26/02/2024 to the following:

[1.] From 1700 hrs 29/02/2024 to 2000 hrs 29/02/2024.
The forecast capacity reserve requirement is 870 MW.
The minimum capacity reserve available is 373 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
X