Update - Direction - SA Region - 12/02/2024
Update - Direction - SA Region - 12/02/2024
Refer Market Notice 114536
The AEMO intervention event that commenced from interval ending 1705 hrs on 12/02/2024 is continuing.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
Direction - VIC region 13/02/2024
Direction - VIC region 13/02/2024
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the VIC region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).
The direction was necessary to maintain the power system in a secure operating state.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1735 hrs on 13/02/2024.
Intervention pricing does not apply to this AEMO intervention event.
Manager NEM Real Time Operations
Possible intervention to manage power system security in VIC region
Possible intervention to manage power system security in VIC region
The synchronous generating units currently expected to be synchronised in VIC from 1830 hrs 13/02/2024 will be inadequate to maintain a secure operating state in VIC .
AEMO estimates that, in the absence of sufficient market response by 1730 hrs 13/02/2024, AEMO may need to intervene by issuing a direction requiring one or more VIC synchronous generating unit(s) to operate or remain synchronised to maintain power system security in VIC.
Manager NEM Real Time Operations
INTENTION TO COMMENCE RERT CONTRACT NEGOTIATIONS
Reliability and Emergency Reserve Trader (RERT) Intention to negotiate for additional reserve - VIC1 Region- 13/02/2024
Refer to AEMO Electricity Market Notice no. 114589.
AEMO intends to commence negotiations with RERT Panel members for the provision of additional reserve by issuing requests for tender for the following period of time;
15:00 to 17:00 hrs 13/02/2024
If reserve is required, the period of activation or dispatch will be within this period but may not be for the entire period.
AEMO will issue a further advice if reserve is contracted.
Manager NEM Real Time Operations
INTENTION TO COMMENCE RERT CONTRACT NEGOTIATIONS
Reliability and Emergency Reserve Trader (RERT) Intention to negotiate for additional reserve - VIC1 Region- 13/02/2024
Refer to AEMO Electricity Market Notice no. 114589.
AEMO intends to commence negotiations with RERT Panel members for the provision of additional reserve by issuing requests for tender for the following period of time;
15:00 to 17:00 hrs 13/02/2024
If reserve is required, the period of activation or dispatch will be within this period but may not be for the entire period.
AEMO will issue a further advice if reserve is contracted.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the VIC Region on 13/02/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following Period:
[1.] From 1430 hrs 13/02/2024 to 1600 hrs 13/02/2024.
The forecast capacity reserve requirement is 562 MW.
The minimum capacity reserve available is 384 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 13/02/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 114532 is cancelled at 1613 hrs 12/02/2024.
Manager NEM Real Time Operations
Direction - SA region 12/02/2024
Direction - SA region 12/02/2024
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).
The direction was necessary to maintain the power system in a secure operating state.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1705 hrs on 12/02/2024.
Intervention pricing does not apply to this AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 13/02/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1630 hrs 13/02/2024 to 1900 hrs 13/02/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1097 MW.
Manager NEM Real Time Operations