Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 14/02/2024
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 14/02/2024
Refer Market Notice 114721
The AEMO Intervention Event and all associated directions are cancelled from 2300 hrs 15/02/2024
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction VIC region 14/02/2024
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction VIC region 14/02/2024
Refer Market Notice 114697
The AEMO Intervention Event and all associated directions are cancelled from 1905 hrs 15/02/2024
Manager NEM Real Time Operations
Update - Direction - SA Region - 14/02/2024
Update - Direction - SA Region - 14/02/2024
Refer Market Notice 114721
The AEMO intervention event that commenced from interval ending 1535 hrs on 14/02/2024 is continuing.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
Cancellation of Distributed PV Contingency 3 (DPVC3), Distributed PV Contingency 2 (DPVC2) and Distributed PV Contingency 1 (DPVC1) condition in the SA Region on 15/02/2024.
Cancellation - DPVC3, DPVC2 and DPVC1 - SA Region
Refer Market Notice 114751 for DPVC3, 114753 for DPVC2 and 114746 for DPVC1.
The DPVC3, DPVC2 and DPVC1 condition for 15/02/2024 is cancelled at 1415 hrs 15/02/2024.
Manager NEM Real Time Operations
Update: Significant power system event - Victoria Region - Hazelwood transformers and Hazelwood PS - Jeeralang No 2 220kV -13/02/2024
Update - Significant power system event - 13/02/2024
Refer AEMO Electricity Market Notices 114685
At 1247 hrs 15/02/2024 the Hazelwood PS - Jeeralang No 2 220kV line was returned to service in the Victoria region
All of the equipment has now been returned to service.
The cause of this significant power system event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Update - Distributed PV Contingency 3 (DPVC3) in the SA Region on 15/02/2024
Update - Distributed PV Contingency 3 (DPVC3) in the SA Region on 15/02/2024
Refer AEMO Electricity Participant Notice 114751
Distributed PV curtailment is occurring in the SA region to maintain system security due to a Distributed PV Contingency condition.
The instruction direction under National Electricity Law s116 to maintain demand above the required threshold is now expected to end at 1430 hrs 15/02/2024.
Manager NEM Real Time Operations
Distributed PV Contingency 2 (DPVC2) in the SA Region on 15/02/2024
AEMO has taken action(s) to maintain power system security in South Australia at 1215 hrs 15/02/2024 due to a forecast Distributed PV Contingency (DPVC) condition.
AEMO actions may include the recall of planned outages, a direction and/or instruction to scheduled and non-scheduled generation, and/or an instruction direction to maintain DPV generation below a secure DPV generation threshold.
Manager NEM Real Time Operations
[EventId:202402151230_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 15 February 2024 12:30
Issued by Australian Energy Market Operator Ltd at 1230 hrs on 15 February 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 February 2024.
Refer to market notice: 114749
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1230 hrs on 15 February 2024.
This is an AEMO autogenerated Market Notice.
Distributed PV Contingency 3 (DPVC3) in the SA Region on 15/02/2024
Distributed PV curtailment is occurring in the SA region to maintain system security due to a Distributed PV Contingency condition.
The instruction direction under National Electricity Law s.116 to maintain demand above the required threshold is expected to end at 1330 hrs 15/02/2024.
Manager NEM Real Time Operations