114152RESERVE NOTICE02/02/2024 12:38:18 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 05/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 114150 is cancelled at 1200 hrs 02/02/2024.

No LOR2 condition is currently forecast in the STPASA period.

AEMO Operations
114150RESERVE NOTICE02/02/2024 12:12:14 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 05/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 114143 has been updated at 1100 hrs 02/02/2024 to the following:

From 1500 hrs to 1700 hrs 05/02/2024.
The forecast capacity reserve requirement is 690 MW.
The minimum capacity reserve available is 640 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
114148GENERAL NOTICE02/02/2024 10:30:00 AM

NEM Local Temperature Alerts for NSW, SA, VIC from 02 Feb 2024 to 06 Feb 2024

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

NSW
Mudgee Ap (39+ Deg C): 4th Feb
Yass (39+ Deg C): 4th Feb

SA
Clare High School (39+ Deg C): 4th Feb
Port Augusta Ap (39+ Deg C): 3rd Feb, 4th Feb

VIC
Mildura Ap (39+ Deg C): 4th Feb

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
114143RESERVE NOTICE02/02/2024 09:41:32 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 05/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1430 hrs to 1730 hrs 05/02/2024.
The forecast capacity reserve requirement is 685 MW.
The minimum capacity reserve available is 396 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
114136NON-CONFORMANCE01/02/2024 10:05:12 PM

NON-CONFORMANCE Region QLD1 Thursday, 1 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 1 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 01/02/2024 21:40 to 01/02/2024 22:05
Amount: -24 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
114131NON-CONFORMANCE01/02/2024 06:40:12 PM

NON-CONFORMANCE Region QLD1 Thursday, 1 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 1 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 01/02/2024 18:30 to 01/02/2024 18:40
Amount: 50 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
114122MARKET INTERVENTION01/02/2024 04:00:09 PM

Update - Direction - SA Region - 28/01/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Direction - SA Region - 28/01/2024

Refer Market Notice 113930

The AEMO intervention event that commenced from interval ending 1705 hrs on 28/01/2024 is continuing.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

Manager NEM Real Time Operations
114114NON-CONFORMANCE01/02/2024 01:45:21 PM

NON-CONFORMANCE Region QLD1 Thursday, 1 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 1 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 01/02/2024 12:25 to 01/02/2024 13:45
Amount: -44 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
114098RESERVE NOTICE01/02/2024 08:54:16 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 06/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 114096 is cancelled at 0800 hrs 01/02/2024.

No LOR2 condition is currently forecast in the STPASA period.

AEMO Operations