114475MARKET INTERVENTION10/02/2024 04:36:24 PM

Update - Direction - SA Region - 04/02/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Direction - SA Region - 04/02/2024

Refer Market Notice 114458

The AEMO intervention event that commenced from interval ending 1635hrs on 04/02/2024 is continuing.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

Manager NEM Real Time Operations
114466NON-CONFORMANCE10/02/2024 10:55:13 AM

NON-CONFORMANCE Region VIC1 Saturday, 10 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Saturday, 10 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: GANNSF1
Duration: 10/02/2024 10:40 to 10/02/2024 10:55
Amount: 25 MW
Constraint: NC-V_GANNSF1

Auto-generated on behalf of Manager NEM Real Time Operations
114459MARKET SYSTEMS09/02/2024 03:04:19 PM

CHG0083624 | Production | A production site transfer of the Electricity and Gas B2B Hub will be carried out to facilitate maintenance activities.

Change Number: CHG0083624
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Gas Hub

Change Title: A production site transfer of the Electricity and Gas B2B Hub will be carried out to facilitate maintenance activities.

Change Start Date & Time: 18/02/2024 09:00:00 AEST
Change End Date & Time: 18/02/2024 17:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production

Participant Impact and Requirements: The following impacts are expected during this maintenance:
- All access to the Electricity B2B Hub will be unavailable.
- All access to the Gas B2B Hub and all ebXML gateways (AEMOMIBB, AGNLGWY, LVI & VENCORP) will be unavailable. CATS and MDMT transactions for VIC/QLD will be delayed during the maintenance window.
- Users are not required to take any action due to this change, however will need to enact manual workarounds for the outage period.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
114458MARKET INTERVENTION09/02/2024 04:04:43 PM

Update - Direction - SA Region - 04/02/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Direction - SA Region - 04/02/2024

Refer Market Notice 114245

The AEMO intervention event that commenced from interval ending 1635hrs on 04/02/2024 is continuing.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

Manager NEM Real Time Operations
114446MARKET INTERVENTION08/02/2024 05:14:11 PM

Update - Direction - SA Region - 04/02/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Direction - SA Region - 04/02/2024

Refer Market Notice 114245

The AEMO intervention event that commenced from interval ending 1635hrs on 04/02/2024 is continuing.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

Manager NEM Real Time Operations
114421NON-CONFORMANCE07/02/2024 03:50:18 PM

NON-CONFORMANCE Region QLD1 Wednesday, 7 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 7 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 07/02/2024 15:40 to 07/02/2024 15:50
Amount: -37 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
114420MARKET INTERVENTION07/02/2024 04:01:24 PM

Update - Direction - SA Region - 04/02/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Direction - SA Region - 04/02/2024

Refer Market Notice 114245

The AEMO intervention event that commenced from interval ending 1635hrs on 04/02/2024 is continuing.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

Manager NEM Real Time Operations
114416NON-CONFORMANCE07/02/2024 02:05:15 PM

NON-CONFORMANCE Region VIC1 Wednesday, 7 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Wednesday, 7 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: GLRWNSF1
Duration: 07/02/2024 14:00 to 07/02/2024 14:05
Amount: 103 MW
Constraint: NC-V_GLRWNSF1

Auto-generated on behalf of Manager NEM Real Time Operations
114390PRICES SUBJECT TO REVIEW06/02/2024 05:40:23 PM

[EventId:202402061745_review] Prices for interval 06-Feb-2024 17:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1740 hrs on 6 February 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 06-Feb-2024 17:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs