113912RESERVE NOTICE28/01/2024 03:01:21 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 04/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1730 hrs 04/02/2024 to 1830 hrs 04/02/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1095 MW.


Manager NEM Real Time Operations
113911RESERVE NOTICE28/01/2024 03:04:01 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 30/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 113859 has been updated at 1430 hrs to the following:

[1.] From 0830 hrs 30/01/2024 to 0900 hrs 30/01/2024.
The forecast capacity reserve requirement is 840 MW.
The minimum capacity reserve available is 806 MW.

[2.] From 1130 hrs 30/01/2024 to 1330 hrs 30/01/2024.
The forecast capacity reserve requirement is 840 MW.
The minimum capacity reserve available is 808 MW.

[3.] From 1400 hrs 30/01/2024 to 1430 hrs 30/01/2024.
The forecast capacity reserve requirement is 840 MW.
The minimum capacity reserve available is 834 MW.

Manager NEM Real Time Operations
113910RESERVE NOTICE28/01/2024 02:58:55 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 29/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 113907 is cancelled at 1445 hrs 28/01/2024.

Manager NEM Real Time Operations
113907RESERVE NOTICE28/01/2024 01:10:25 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 29/01/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Periods:

[1.] From 1730 hrs 29/01/2024 to 1830 hrs 29/01/2024.
The forecast capacity reserve requirement is 1043 MW.
The minimum capacity reserve available is 872 MW.

[2.] From 1930 hrs 29/01/2024 to 2100 hrs 29/01/2024.
The forecast capacity reserve requirement is 1075 MW.
The minimum capacity reserve available is 636 MW.


Manager NEM Real Time Operations
113902RESERVE NOTICE28/01/2024 06:40:51 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 28/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 113857 is cancelled at 0640 hrs 28/01/2024.

Manager NEM Real Time Operations
113880PRICES SUBJECT TO REVIEW27/01/2024 06:10:18 PM

[EventId:202401271815_review] Prices for interval 27-Jan-2024 18:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1810 hrs on 27 January 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Jan-2024 18:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
113878PRICES SUBJECT TO REVIEW27/01/2024 06:05:14 PM

[EventId:202401271810_review] Prices for interval 27-Jan-2024 18:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1805 hrs on 27 January 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Jan-2024 18:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
113877PRICES SUBJECT TO REVIEW27/01/2024 06:00:15 PM

[EventId:202401271805_review] Prices for interval 27-Jan-2024 18:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1800 hrs on 27 January 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Jan-2024 18:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
113876PRICES SUBJECT TO REVIEW27/01/2024 05:55:18 PM

[EventId:202401271800_review] Prices for interval 27-Jan-2024 18:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1755 hrs on 27 January 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Jan-2024 18:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.