118771GENERAL NOTICE11/10/2024 08:25:55 AM

Heywood testing (SA to Vic) 11th October 2024

AEMO ELECTRICITY MARKET NOTICE

There is an opportunity for testing Heywood Interconnector (HIC) flow from South Australia to Victoria above 450MW and Victoria to South Australia above 450MW on 11th October from 8:00hrs to 19:00hrs

This test includes a trip and reclose of a line in South Australia.

Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.

Ben Blake
AEMO Operations
     
118698RESERVE NOTICE09/10/2024 10:52:16 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region [beginning] on 09/10/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 118694 is cancelled at 1050 hrs 09/10/2024.

Manager NEM Real Time Operations
     
118694RESERVE NOTICE09/10/2024 08:50:05 AM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 09/10/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1800 hrs 09/10/2024 to 1830 hrs 09/10/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1393 MW.

Manager NEM Real Time Operations
     
118691RESERVE NOTICE08/10/2024 04:37:04 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 09/10/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 118671 is cancelled at 1630 hrs 08/10/2024.

Manager NEM Real Time Operations
     
118671RESERVE NOTICE08/10/2024 01:32:33 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 09/10/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:

[1.] From 1730 hrs 09/10/2024 to 1930 hrs 09/10/2024.
The forecast capacity reserve requirement is 1144 MW.
The minimum capacity reserve available is 951 MW.

Manager NEM Real Time Operations
     
118666RESERVE NOTICE08/10/2024 05:58:20 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/10/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 118665 is cancelled at 0555 hrs 08/10/2024.

Manager NEM Real Time Operations
     
118665RESERVE NOTICE07/10/2024 11:08:07 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/10/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 118664 has been updated at 2300 hrs to the following:

[1.] From 1730 hrs 08/10/2024 to 1900 hrs 08/10/2024.
The forecast capacity reserve requirement is 1198 MW.
The minimum capacity reserve available is 1045 MW.

Manager NEM Real Time Operations
     
118664RESERVE NOTICE07/10/2024 09:31:50 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/10/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 118648 has been updated at 2130 hrs to the following:

[1.] From 1730 hrs 08/10/2024 to 1930 hrs 08/10/2024.
The forecast capacity reserve requirement is 1187 MW.
The minimum capacity reserve available is 863 MW.

Manager NEM Real Time Operations
     
118648RESERVE NOTICE07/10/2024 02:31:27 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/10/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 118642 has been updated at 1430 hrs to the following:

[1.] From 1730 hrs 08/10/2024 to 1900 hrs 08/10/2024.
The forecast capacity reserve requirement is 1166 MW.
The minimum capacity reserve available is 1005 MW.

Manager NEM Real Time Operations
     