117261NON-CONFORMANCE01/07/2024 03:30:13 PM

NON-CONFORMANCE Region NSW1 Monday, 1 July 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Monday, 1 July 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: QBYNBG1, QBYNBL1
Aggregate Dispatch Group: QBYNBESS_ADG1
Duration: 01/07/2024 14:35 to 01/07/2024 15:30
Amount: 10 MW
Constraint: NC-N_QBYNBESS_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
117238GENERAL NOTICE28/06/2024 08:43:51 AM

Fast Frequency Response Market - Dispatch of R1 and L1 FCAS in the SA region during island conditions from 1 July 2024

AEMO ELECTRICITY MARKET NOTICE

From 1 July 2024 AEMO will dispatch R1 and L1 FCAS locally in the SA region during conditions of actual islanding of the SA region.

This follows the end of contracts for Fast Frequency Response (FFR) in the SA region.

The dispatch of R1 and L1 FCAS under these island conditions will not be capped.

These changes are only applicable for conditions of actual SA islanding from the rest of the NEM.

No other changes to the dispatch of R1 and L1 FCAS will be made on this date.

For information on the Fast Frequency Response (FFR) initiative please visit the website at: https://www.aemo.com.au/initiatives/major-programs/fast-frequency-response

Andrew Groom
AEMO Operations
117215NON-CONFORMANCE27/06/2024 01:00:18 PM

NON-CONFORMANCE Region QLD1 Thursday, 27 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 27 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 27/06/2024 12:40 to 27/06/2024 13:00
Amount: -45 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
117131NON-CONFORMANCE25/06/2024 09:50:20 AM

NON-CONFORMANCE Region QLD1 Tuesday, 25 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Tuesday, 25 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 25/06/2024 09:35 to 25/06/2024 09:50
Amount: -40 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
117125NON-CONFORMANCE24/06/2024 08:21:08 PM

NON-CONFORMANCE Region QLD1 Monday, 24 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 24 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 24/06/2024 18:30 to 24/06/2024 20:20
Amount: 49 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
117124NON-CONFORMANCE24/06/2024 08:20:17 PM

NON-CONFORMANCE Region QLD1 Monday, 24 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 24 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 24/06/2024 19:30 to 24/06/2024 20:20
Amount: -42 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
117113NON-CONFORMANCE24/06/2024 07:00:21 AM

NON-CONFORMANCE Region QLD1 Monday, 24 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 24 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 24/06/2024 06:40 to 24/06/2024 07:00
Amount: 19 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
117111NON-CONFORMANCE23/06/2024 08:00:16 PM

NON-CONFORMANCE Region QLD1 Sunday, 23 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 23 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 23/06/2024 19:05 to 23/06/2024 20:00
Amount: -35 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
117105NON-CONFORMANCE23/06/2024 12:55:20 PM

NON-CONFORMANCE Region QLD1 Sunday, 23 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 23 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 23/06/2024 12:15 to 23/06/2024 12:55
Amount: -29 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations