113992SETTLEMENTS RESIDUE29/01/2024 05:56:27 PM

[EventId:202401291755_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 29 January 2024 17:55

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1755 hrs on 29 January 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 29 January 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.

The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1755 hrs on 29 January 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
113985SETTLEMENTS RESIDUE29/01/2024 04:30:21 PM

[EventId:202401291630_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 29 January 2024 16:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1630 hrs on 29 January 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 January 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1630 hrs on 29 January 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
113983NON-CONFORMANCE29/01/2024 04:05:13 PM

NON-CONFORMANCE Region NSW1 Monday, 29 January 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Monday, 29 January 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: TALWA1
Duration: 29/01/2024 16:00 to 29/01/2024 16:05
Amount: 66 MW
Constraint: NC-N_TALWA1

Auto-generated on behalf of Manager NEM Real Time Operations
113979RESERVE NOTICE29/01/2024 03:22:26 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 05/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

From 1830 hrs to 1900 hrs 05/02/2024.
The forecast capacity reserve requirement is 1254 MW.
The minimum capacity reserve available is 1187 MW.

AEMO Operations
113978RESERVE NOTICE29/01/2024 03:13:45 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 05/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1430 hrs to 2200 hrs 05/02/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 730 MW.

AEMO Operations
113976RESERVE NOTICE29/01/2024 03:10:28 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 04/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 113912 has been updated at 1400 hrs 29/01/2024 to the following:

From 1700 hrs to 2130 hrs 04/02/2024.
The forecast capacity reserve requirement is 1489 MW.
The minimum capacity reserve available is 1108 MW.

AEMO Operations
113972MARKET INTERVENTION29/01/2024 04:18:46 PM

Update - Direction - SA Region - 28/01/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Direction - SA Region - 28/01/2024

Refer Market Notice 113930

The AEMO intervention event that commenced from interval ending 1705 hrs on 28/01/2024 is continuing.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

Manager NEM Real Time Operations
113966RESERVE NOTICE29/01/2024 11:07:25 AM

PDPASA - Update to Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 29/01/2024

AEMO ELECTRICITY MARKET NOTICE

Refer to MN 113962

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:

[1.] From 1730 hrs 29/01/2024 to 1930 hrs 29/01/2024.
The forecast capacity reserve requirement is 1106 MW.
The minimum capacity reserve available is 965 MW.


Manager NEM Real Time Operations
113962RESERVE NOTICE29/01/2024 09:52:11 AM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 29/01/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:

[1.] From 1830 hrs 29/01/2024 to 1900 hrs 29/01/2024.
The forecast capacity reserve requirement is 1035 MW.
The minimum capacity reserve available is 928 MW.