116852PRICES SUBJECT TO REVIEW31/05/2024 11:15:27 AM

[EventId:202405311120_review] Prices for interval 31-May-2024 11:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1115 hrs on 31 May 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 31-May-2024 11:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
116850PRICES SUBJECT TO REVIEW31/05/2024 11:10:28 AM

[EventId:202405311115_review] Prices for interval 31-May-2024 11:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1110 hrs on 31 May 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 31-May-2024 11:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
116827MARKET INTERVENTION28/05/2024 02:14:41 PM

Direction - SA region 28/05/2024

AEMO ELECTRICITY MARKET NOTICE.

Direction - SA region 28/05/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1415 hrs on 28/05/2024.

Intervention pricing does not apply to this AEMO intervention event.

Manager NEM Real Time Operations
116825MARKET INTERVENTION28/05/2024 11:04:08 AM

Update - Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Possible intervention to manage power system security in SA region

Refer AEMO Electricity Market Notice 116824

The synchronous generating units currently expected to be synchronised in SA from 0000 hrs 29/05/2024 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 1400 hrs 28/05/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
116824MARKET INTERVENTION27/05/2024 05:11:00 PM

Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA region

The synchronous generating units currently expected to be synchronised in SA from 0000 hrs 29/05/2024 will be inadequate to maintain a secure operating state in SA.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
116822RESERVE NOTICE27/05/2024 02:56:58 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 03/06/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1730 hrs to 1830 hrs 03/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1751 MW.

AEMO Operations
116821MARKET INTERVENTION27/05/2024 02:35:30 PM

Cancellation - Possible intervention to manage power system security in SA region 28/05/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Possible intervention to manage power system security in SA region 28/05/2024

Refer Market Notice 116819

AEMO no longer foresees a possible requirement for intervention to manage power system security in SA region. The advice of possible intervention is cancelled from 1435 hrs 27/05/2024.

Manager NEM Real Time Operations
116819MARKET INTERVENTION27/05/2024 12:58:21 PM

Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA region

The synchronous generating units currently expected to be synchronised in SA from 1030 hrs 28/05/2024 will be inadequate to maintain a secure operating state in SA.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
116818MARKET INTERVENTION27/05/2024 09:35:24 AM

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 26/05/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 26/05/2024

Refer Market Notice 116814

The AEMO Intervention Event and all associated directions are cancelled from 0935 hrs 27/05/2024

Manager NEM Real Time Operations