Inter-regional transfer limit variation - Tamworth - Armidale No. 86 330 kV Line - NSW region - 19/05/2024
Inter-regional transfer limit variation - Tamworth - Armidale No. 86 330 kV Line - NSW region - 19/05/2024
A planned outage of Tamworth - Armidale No. 86 330 kV Line in the NSW region was scheduled from 0800 hrs 07/05/2024 to 1800 hrs 20/05/2024.
The outage has been rescheduled to be completed by 1200 hrs 19/05/2024.
Constraint set(s) invoked:
N-ARTW_86
N-DM_SVC
N-TW_SVC
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW1-QLD1
T-V-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - DAPTO - MARULAN 8 330KV Line- NSW region - 18/05/2024
Inter-regional transfer limit variation - DAPTO - MARULAN 8 330KV Line - NSW region - 18/05/2024
A planned outage of DAPTO - MARULAN 8 330KV Line in the NSW region was scheduled from 0830 hrs 27/04/2024 to 1200 hrs 20/05/2024.
The outage has been completed at 1750 hrs 18/05/2024.
Constraint set(s) revoked: N-DTMN_8_15M, N-X_3L+8
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,
NSW1-QLD1,
V-S-MNSP1
VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
[EventId:202405150700_review] Prices for interval 15-May-2024 07:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 0655 hrs on 15 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 15-May-2024 07:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405150655_review] Prices for interval 15-May-2024 06:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 0650 hrs on 15 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 15-May-2024 06:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405150650_review] Prices for interval 15-May-2024 06:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 0645 hrs on 15 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 15-May-2024 06:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405150645_review] Prices for interval 15-May-2024 06:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 0640 hrs on 15 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 15-May-2024 06:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405150640_review] Prices for interval 15-May-2024 06:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 0635 hrs on 15 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 15-May-2024 06:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405150635_review] Prices for interval 15-May-2024 06:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 0630 hrs on 15 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 15-May-2024 06:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Inter-regional transfer limit variation - Blyth West to Munno Para 275 kV line - SA region - 08/05/2024
Inter-regional transfer limit variation - Blyth West to Munno Para 275 kV line - SA region - 08/05/2024
At 1536 hrs 08/05/2024 there was an unplanned outage of Blyth West to Munno Para 275 kV line.
The following constraint set(s) invoked at 1545 hrs 08/05/2024
S-X_BGBW+BWMP
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations